HomeMy WebLinkAbout07.01.2025 Planning Commission Meeting
MINUTES
CITY OF COLUMBIA HEIGHTS
PLANNING COMMISSION MEETING
July 01, 2025
The meeting was called to order at 6:00 pm by Chair Wolfe.
CALL TO ORDER/ROLL CALL
Commissioners present: Jeffrey Johnson, Dirk Schmitz, Karl Rehfuss, Paul Moses, and Clara Wolfe
Commissioners absent: John Gianoulis, Ahmed Maameri
Also present: Aaron Chirpich, City Manager; Sarah LaVoie, Administrative Assistant; Mitch Forney,
Community Development Director; Laurel Deneen, Council Liaison.
APPROVAL OF MINUTES
1. Approval of June 03, 2025 Planning Commission Meeting Minutes
Motion by Schmitz, seconded by Johnson, to approve the minutes from the meeting of June 03,
2025. All ayes. MOTION PASSED.
PUBLIC HEARINGS
2. Shoreland Overlay District Variance to exceed the 35% impervious surface lot coverage to allow
for the construction of a multi-phased redevelopment project at 800 53rd Avenue NE.
Forney explained that the Council would be discussing the Medtronic site project during the July
28th Council meeting and encouraged public comment during that meeting. He introduced HKGI
Consulting Planner Rita Trapp, who is filling in for the City since the previous City Planner left the
City.
Introduction: HKGI Consulting Planner Rita Trapp stated that Kaas Wilson Architects, on behalf of
Lincoln Avenue Communities, has submitted a shoreland variance application to exceed the 35%
impervious surface lot coverage limit. This request is part of the multi-phase Medtronic
redevelopment project, located at the 11.74-acre vacant Medtronic corporate campus abutting
Sullivan Lake. The entire property is located within the Shoreland Overlay District as it is within
1,000 feet of the lake. The proposed plans and preliminary plat show an impervious surface
coverage exceeding the maximum allowed under the City’s shoreland regulations. Therefore, a
variance is required to permit the impervious surface beyond the 35% threshold.
Ms. Trapp noted that the proposed project includes demolishing the existing Medtronic building
and redeveloping the site into a multi-phased project entailing two 6-story, 132-unit affordable
multifamily buildings, a mixed-use building with 12,000 sq. ft. of commercial space, and a range of
150–175-unit market-rate apartments, 58 townhomes, and associated park and infrastructure
improvements as well as multi-modal transportation facilities. The property is still owned by
Medtronic, but under a purchase agreement with the applicant/developer. The Planning
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 2
Commission has reviewed and recommended for approval with conditions the Preliminary Plat,
Planned Unit Development - Mixed Use Development, and Easement Vacation. Additional project
information can be found in the June 3, 2025, Planning Commission staff report.
Forney explained that the current Shoreland Overlay District Ordinance, last amended in 2008, is
intended to guide the development along shoreland of public waters. An overlay buffer is applied
on property within 1,000 feet of a designated waterway, as determined by the Department of
Natural Resources (DNR). Since the proposed project’s property is abutting Sullivan Lake, which is
designated as a General Development Lake, development must follow the standards of the
shoreland overlay district, including the maximum amount of impervious surface.
Ms. Trapp noted that currently, the site consists of the former 135,000 square foot Medtronic
building and an 812-stall bituminous parking lot. According to the project’s development plans,
there is currently 54% of impervious surface coverage, which is approximately 296,208 square feet
or 6.8 acres. It is important to note that the Medtronic site was built in 1979 with no stormwater
treatment. As this was before the current DNR regulations were adopted, the property is
nonconforming.
Ms. Trapp explained that the proposed project includes a multi-phase, full-site redevelopment with
several new buildings and reconfigured parking and circulation. The proposal increases the existing
impervious surface on the property from 54% to 67.7%. A lot -by-lot impervious surface breakdown
is attached. Although the project will be phased, processing one shoreland variance permit will
allow for a streamlined approval process and construction timeline. In order to meet the City
requirements, the project must receive approval of the shoreland variance and ensure proper
stormwater management. As part of the recent approval, the applicant has demonstrated
adequate stormwater management utilizing various infiltration features for the site.
Ms. Trapp mentioned that, as there is currently no existing treatment on-site, the proposed
improvements will reduce runoff volumes and improve water quality. In addition, the applicant will
also meet the MPCA’s NPDES stormwater permit requirements. It is projected that the stormwat er
features will be installed in the initial construction phases with the affordable housing project.
Ms. Trapp stated that due to the size and complexity of the project, the shoreland variance
requires two tiers of review criteria for City review and consideration. The first tier is the City’s
standard variance criteria, and the second tier is the shoreland overlay district variance
requirements.
Ms. Trapp reviewed the provisions from Section 9.104 (G) outlining the City’s standard variance
findings of fact that are required before granting a variance.
(a) Because of the particular physical surroundings, or the shape, configuration, topography, or
other conditions of the specific parcel of land involved, strict adherence to the provisions of this
article would cause practical difficulties in conforming to th e zoning ordinance. The applicant,
however, is proposing to use the property in a reasonable manner not permitted by the zoning
ordinance.
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 3
Staff Comment: The applicant is proposing to use the property in a reasonable manner not
permitted by the zoning ordinance through a unique development proposal that offers higher
quality land usage and amenities that follow the intent of the Comprehensive Plan and city-
generated concepts for the site. The approval of a shoreland variance will allow for the
construction of the project as proposed.
(b) The conditions upon which the variance is based are unique to the specific parcel of land
involved and are generally not applicable to other properties within the same zoning
classification.
Staff Comment: The existing property is a relatively large site that has been vacated and is not able
to be sold to a new commercial user. The proposed development, as outlined in the preliminary
plat and development plan, represents an efficient and beneficial use of the land, aligning with the
highest and best use principles while also addressing key community needs. Importantly, the
proposed impervious surfaces will be situated over 200 feet from Sullivan Lake, with Sulli van Lake
Park serving as a natural buffer. The developer has committed to parkland improvements that will
help mitigate runoff and prevent erosion, thereby protecting the lake’s ecological health.
Additionally, the City Engineer has approved the schematic design, and city staff are coordinating
with the DNR and the Mississippi Watershed Management Organization to address any additional
stormwater concerns. The development will incorporate new stormwater filtration systems, which
are an improvement over the current site, which lacks any such infrastructure. Given that Central
Avenue currently has no stormwater filtration, incremental improvements on sites between
Central Avenue and Sullivan Lake will contribute positively to the area’s environmental
management.
(c) The practical difficulties are caused by the provisions of this article and have not been created
by any person currently having a legal interest in the property.
Staff Comment: The site presents practical challenges, notably that it currently exceeds the
Shoreland District’s impervious surface limit of 35%, with existing coverage at approximately 54%
and no stormwater treatment in place. While the proposed development will result in a modest
increase in impervious surface, it will also incorporate enhanced stormwater management
features. These improvements are designed to offset the net increase in hard cover by promoting
better water quality and providing added environmental and recreational benefits for the City.
(d) The granting of the variance is in harmony with the general purpose and intent of the
Comprehensive Plan.
Staff Comment: The Comprehensive Plan supports the redevelopment of this site. In addition, the
Comprehensive Plan supports mixed-use development and transit-oriented development, which is
implemented through this proposal.
(e) The granting of the variance will not be materially detrimental to the public welfare or
materially injurious to the enjoyment, use, development, or value of property or improvements
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 4
in the vicinity.
Staff Comment: Granting the shoreland variance would not be detrimental to the public welfare or
materially injurious to the enjoyment, use, development, or value of property in the vicinity. The
project will improve the land usage of the site by providing a mix of buildings and use types, as well
as amenities, increasing the value of property and amenities in the city.
As part of the second tier of review criteria, the City may establish reasonable conditions that are
deemed necessary to mitigate adverse impacts directly associated with the granting of the variance
and to protect neighboring properties. Since the variance is related to the Shoreland Overlay
District, Staff are recommending that the additional conditions set forth in the Overlay District
Section 9.114 (C) shall apply. The provisions below outline the additional review criteria that must
be met in order for the City to grant a variance in the shoreland and exceed the impervious surface.
They are as follows:
i. All structures, additions, or expansions shall meet setback and other requirements of this
code.
ii. The lot shall be served with municipal sewer and water.
iii. The lot shall provide for the collection and treatment of stormwater in compliance with
Chapter 9 of the city code if determined that the site improvements will result in increased
runoff directly entering a public water. All development plans shall require review and
approval by the City Engineer and the underlying watershed district
iv. Measures will be taken for the treatment of stormwater runoff and/or prevention of
stormwater from directly entering a public water. The measures may include, but are not
limited to the following:
a. Appurtenances as sedimentation basins, debris basins, desilting basins, or silt traps.
b. Installation of debris guards and micro silt basins on store sewer inlets.
c. Use where practical, oil skimming devices or sump catch basins.
d. Direct drainage away from the lake and into pervious, grassed yards through site
grading, use of gutters and downspouts.
e. Construction of sidewalks of partially pervious raised materials such as decking,
which has natural earth or other pervious material beneath or between the
planking.
f. Use grading and construction techniques that encourage rapid infiltration, such as
sand and gravel under impervious materials with adjacent infiltration swales graded
to lead into them.
g. Install berms, water bars, or terraces, which temporarily detain water before
dispersing it into the pervious area.
Staff Comment: Ms. Trapp stated the proposed project is meeting setback requirements and is
being processed as Planned Unit Development. The current estimated setback distance from
Sullivan Lakes Ordinary High-Water Level is 180.8 feet. Which city code only requires a setback of
50 ft. The initial review of the project has been recommended for approval, demonstrating that
other requirements have been met or are undergoing separate reviews. The site is currently served
by municipal sewer and water. The proposed development will also provide utility improvements
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 5
to expand the capacity and accommodate additional demand, and add stormwater management.
Recommendation: Staff recommends approval of the shoreland variance as presented , subject to
the conditions outlined below:
1. The applicant shall adhere to all stormwater requirements and permitting required by state and
local codes, permits, licenses, and inspections will be met and in full compliance.
Questions/Comments from Members:
Schmitz asked if the system would work fast enough since the water table is by the lake. He asked if
there was an overflow option if the system became full. He asked to clarify the storm basin diagram
and asked what the depth of it was. He asked if it would be sod covered of deeper with native
plantings. Forney stated that the storm basin would be under the parking areas. Civil Engineer, PJ
Disch, explained that there would be three tanks that are three feet above groundwater, with a
sand basin in the middle, to meet MPCA standards. The outlet of the tanks will be designed
underneath the elevation. The first 1.1 inch of water in a storm event would not go into the lakes
but would go into the tanks, and the ground would infiltrate into the ground. After that, there
would be a control structure on each tank that would allow the stormwater to discharge at a
certain rate. He explained that while the impervious surface will increase on the site due to the
project, there is no stormwater treatment currently, so having a stormwater treatment added to
the project will help the site. The tanks have the capacity to hold up to a 100-degree storm event,
and then it would slowly discharge into the City storm sewer before draining into the lake. He
added that the storm basin would be similar to a rain garden.
Moses asked if there was a proposed filtration system. Mr. Disch replied that the tanks were
infiltration.
Public Hearing Opened.
Wolfe opened the Public Hearing.
Lori Averette Osbourne read a letter from Karen Smith, who is an administrator at Little Voyagers
Montessori, which is inside St. Timothy Lutheran Church. The letter read that Ms. Smith “felt like
the density of the planned property is too high and there is no green space in the design , which is
required. Requesting a variance is telling you that there is more development planned than there is
space. The number of buildings, proposed residents, and businesses is more than the property size
by the City Code. Therefore, the variance should not be approved. It is the responsibility of the
Planning Commission and the City Council to abide by the Code. Yes, variances can be requested.
My concern is that no one seems to be listening to lifetime residents and how it truly affects the
lifestyle of the people in the area. The density of the area will flow over to a nearby park and the
streets. It appears that the park is being considered as the green space for the development. This is
not the purpose of the City parks. It is additional space to gather family homes, have some green
space, and a development is required to provide some green space, especially one of this size. The
nature and wildlife that are unique to Sullivan Lake Park are used by local families, wildlife, and
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 6
area learning programs, and it will be overtaken and destroyed. There is a reason that cities require
green space in new developments. Please do not give up the uniqueness of the area that the City
designed for the community for a developer, and their bottom line, and the City’s bottom line.
Please maintain quality areas for all families to enjoy, and want to live in that area. The Planning
Commission and the City Council are responsible for zoning and City Codes and for the quality of
life within the City. Do not allow the variance for this project. If the project needs to go through, it
can be redesigned to fit the area within the Code that protects the community. Please consider
this: where would you choose to live, either in the development or beside it? This developer is not
from the area, and it does not affect their lifestyle. Please really consider the feedback from the
residents in their City. An additional thought, there is no possible truth that there will not be a big
increase in traffic on 53rd Avenue. Since changes were made at the light on University Avenue, I
avoid that area and use residential streets to go north on 694. Thank you for your time and
consideration.”
Walter Horishnyk, City resident, asked if there is a specific height requirement that designates
commercial use for buildings in the commercial zoning district. Forney replied that there are, and
he could look up the information. Mr. Horishnyk explained that if there is a zoning requirement
that does not allow a commercial site to go to six stories high, why would there be a variance that
is granted for a residential apartment. He asked if there was an environmental study on a four-
story building instead of a six-story building. He wondered if there was any difference between the
two regarding bird migration, or environmental impacts on the nature around the park. He strongly
advised not to go over four stories because all around the surrounding area in the City, only go to
four stories. He suggested not including the fitness court in the project because it has a lot of
concrete and goes against having more nature, since it takes away the green space. He added that
Sullivan Lake Park is small and that there are other areas in the City that have more space for a
fitness court. Forney explained that he could not find the height limit , but he would follow up with
the Planning Commission. He added that the City is still accepting comments on the environmental
assessment worksheet. He recommended that community members provide comments through
July 10th. He noted that comments are accepted through the City’s website. The Parks and
Recreation Commission and the City Council will address the fitness court at the park.
Ann Scanlon, City resident, explained that she is opposed to the project and expressed her
understanding that the City needs to adjust housing and put something on the site. She added that
she disagrees with the scope and size of the project. She mentioned that the 180-foot variance that
was discussed is too small and does not give enough space for wildlife. She stated that more
impervious surface would be added to the park and to the development . She wondered how
adding a pickleball court and fitness court would add green space. She asked if the City cared about
the residents in the area. She explained that by putting in much into the site, it is destroying
habitats for wildlife. She agreed that the Medtronic site needed to be developed and that housing
should be added. She encouraged the commission to see what kind of housing they were putting in
and how they were putting it in. She stated that the commissioners were not doing due diligence if
they passed the variance as is.
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 7
Julienne Wyckoff, City resident, stated that taking away green space is wrong. She explained that
she learned that 85 different species of birds have been seen in Sullivan Lake Park. She encouraged
the Commission to think about all the critters and wildlife that could be hurt due to the
development. She asked if there was a contact person from the DNR that residents could reach out
to. Forney replied that the DNR’s comments will be included in the City Council’s packet moving
forward. The contact person is Alex Cell. He added that he could provide the contact information
and DNR packet after the meeting to residents who were in attendance. Ms. Wyckoff stated that
she would like to see development in the area, but to decrease the density and keep the green
space.
Ms. Scanlon asked who would manage the infiltration tanks after the developer leaves. Forney
replied that the City and the developer would work out a maintenance agreement.
Wolfe explained that the final decisions would be made at the City Council meeting.
Public Hearing Closed.
Motion by Wolfe, seconded by Moses, to close the Public Hearing. All ayes. MOTION PASSED.
Motion by Schmitz, seconded by Rehfuss, to waive the reading of Resolution 2025-057, there being
ample copies available to the public. All ayes. MOTION PASSED.
Motion by Moses, seconded by Wolfe, to recommend that the City Council approve Resolution 2025-
057, a resolution approving a Shoreland Variance for the property located at 800 53rd Avenue NE in
the City of Columbia Heights, MN. All ayes. MOTION PASSED.
OTHER BUSINESS
Forney stated that staff are interviewing candidates for the new City Planner position.
ADJOURNMENT
Motion by Clara Wolfe, seconded by Rehfuss to adjourn the meeting at 6:50 pm. All ayes. MOTION
PASSED
Respectfully submitted,
City of Columbia Heights MINUTES July 01, 2025
Planning Commission Meeting Page 8
Sarah LaVoie, Administrative Assistant