Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
2017-2791
2017 -2791 AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT (STIPULATED PRICE) THIS AGREEMENT is by and between the CITY OF COLUMBIA HEIGHTS, MINNESOTA ( "Owner ") and Northdale Construction Company, Inc. Owner and Contractor hereby agree as follows: ARTICLE 1— WORK ( "Contractor ") 1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: 2017 WATER MAIN CONSTRUCTION — PROJECT 1703 2017 WATER MAIN HYDRANT AND GATE VALVE CONSTRUCTION — PROJECT 1710 ARTICLE 2 — THE PROJECT 2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: CITY PROJECT NO. 1703 ♦ TEMPORARY WATER SERVICE ♦ PIPE REMOVAL /ABANDON ♦ WATER MAIN CONSTRUCTION ♦ SELECT CURB BOX, CURB STOP AND /OR WATER SERVICE REPLACEMENT ♦ CONCRETE AND BITUMINOUS SURFACING ♦ MISCELLANEOUS CONSTRUCTION CITY PROJECT NO. 1710 . ♦ HYDRANT REPLACEMENT MAY 2,7 2017 ♦ MISCELLANEOUS CONSTRUCTION ARTICLE 3 — ENGINEER 3.01 The part of the Project that pertains to the Work has been designed by the CITY OF COLUMBIA HEIGHTS' ENGINEERING DEPARTMENT (ENGINEER). 3.02 The ENGINEER is to act as Owner's representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents. EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1 of 7 ARTICLE 4 — CONTRACT TIMES 4.01 Time of the Essence A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract. 4.02 Contract Times: Dates A. The Work will be substantially completed on or before July 7, 2017, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before August 4, 2017. 4.03 Liquidated Damages A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the Contract. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty): 1. Substantial Completion: Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete. 2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $1,000.00 for each day that expires after such time until the Work is completed and ready for final payment. 3. Liquidated damages for failing to timely attain Substantial Completion and final completion are not additive and will not be imposed concurrently. ARTICLE 5 — CONTRACT PRICE 5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, subject to adjustment under the Contract: A. For all Work, at the prices stated in Contractor's Bid, attached hereto as an exhibit. B. The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer. ARTICLE 6 — PAYMENT PROCEDURES 6.01 Submittal and Processing of Payments A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions. EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2 of 7 6.02 Progress Payments; Retainage A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor's Applications for Payment on or about the 15th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract. 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract a. 95 percent of Work completed (with the balance being retainage). If the Work has been 50 percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage). B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 98 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 200 percent of Engineer's estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment. 6.03 Final Payment A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 15.06. ARTICLE 7 — INTEREST 7.01 All amounts not paid when due shall bear interest at the rate stipulated in Minnesota Statute 161.322. ARTICLE 8 — CONTRACTOR'S REPRESENTATIONS 8.01 In order to induce Owner to enter into this Contract, Contractor makes the following representations: A. Contractor has examined and carefully studied the Contract Documents, and any data and reference items identified in the Contract Documents. B. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work. C. Contractor is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work. EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright OO 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 of 7 D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings. E. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site - related reports and drawings identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (3) Contractor's safety precautions and programs. F. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract. G. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents. H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor. 1. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. J. Contractor's entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents. EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4 of 7 ARTICLE 9 — CONTRACT DOCUMENTS 9.01 Contents A. The Contract Documents consist of the following: This Agreement (pages 1 to 7, inclusive). 1. Performance bond (pages 1 to 3, inclusive). 2. Payment bond (pages 1 to 3, inclusive). 3. Other bonds. a. _(pages _to inclusive). 4. General Conditions (pages 1 to 65, inclusive). 5. Supplementary Conditions (pages 00700 -66 to 00700 -75, inclusive). 6. Specifications as listed in the table of contents of the Project Manual, 7. Drawings (not attached but incorporated by reference) consisting of 2017 Water Main Utility Construction: 9 sheets with each sheet bearing the project number 1703 and/ or 1710. 8. Addenda (numbers 1 to 1, inclusive). 9. Exhibits to this Agreement (enumerated as follows): a. Contractor's Bid (pages 11 to 20, inclusive). 10. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto: a. Notice to Proceed. b. Work Change Directives. c. Change Orders. B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above). C. There are no Contract Documents other than those listed above in this Article 9. D. The Contract Documents may only be amended, modified, or supplemented as provided in the General Conditions. EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 of 7 ARTICLE 10 — MISCELLANEOUS 10.01 Terms A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions. 10.02 Assignment of Contract A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, money that may become due and money that is due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents. 10.03 Successors and Assigns A. Owner and Contractor each binds itself, its successors, assigns, and legal representatives to the other party hereto, its successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents. 10.04 Severability A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. 10.05 Contractor's Certifications A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05: 1. "corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the Contract execution; 2. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non - competitive levels, or (c) to deprive Owner of the benefits of free and open competition; 3. "collusive practice" means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non - competitive levels; and 4. "coercive practice" means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. 10.06 Other Provisions (if applicable). EJCDC® C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 of 7 IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement. This Agreement will be effective on May 8, 2017 (which is the Effective Date of the Contract). OWNER: CONTRACTOR: [CORPORATE SEAL] Attest: t^- Title:'' Address for giving notices: 63738 th Avenue NE Columbia Heights, MN 55421 (If OWNER is a corporation, attach evidence of authority to sign. If OWNER is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of OWNER - CONTRACTOR Agreement.) Designated Representative: Name: Kevin Hansen Title: City Engineer /Public Works Director Address: 63738 th Avenue NE Columbia Heights, MN 55421 Phone: 763 - 706 -3705 [CORPORATE SEAL] ri�Y`C' -° S-i- A) Lqtr4-Q ` Oct Y) ss3� 1 License No.: (Where applicable) Agent for service of process: (if Contractor is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.) Designated Representative: Name: Title: Address: Phone: E)CDC(1 C -520 (Rev. 1), Agreement Between Owner and Contractor for Construction Contract (Stipulated Price). Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7 of 7 Ea CNGINURS JOINT t;0 ? .TRACT DOCUMENTS COMMITTEE CONTRACTOR (name and address): Northdale Construction Company, Inc. 9760 71st Street NE Albertville, MN 55301 OWNER (name and address): City of Columbia Heights 637 38th Avenue N.E. Columbia Heights, MN 55421 CONSTRUCTION CONTRACT SURETY (name and address of principal place of business): The Guarantee Company of North America USA One Towne Square, Suite 1470 Southfield, MI 48076 -3725 Effective Date of the Agreement: May 8, 2017 Amount: $393,924.72 Description (name and location): 2017 Water Main Construction -Project 1703 / 2017 Water Main Hydrant and Gate Valve Construction - Project 1710 BOND Bond Number: 16145092 Date (not earlier than the Effective Date of the Agreement of the Construction Contract): May 11, 2017 Amount: $393,924.72 Modifications to this Bond Form: ® None ❑ See Paragraph 16 Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Performance Bond to be duly executed by an authorized officer, agent, or representative. CONTRACTOR AS PRINCIPAL SURETY Northdale Construction Company, Inc. The Guarantee Company of North America USA (seal) (seat) Contr r s me and Corporate Seal Surety's Name. and Corporate S Signature Signature (attach power of attorney) Philip B. Lesnar Rachel Thomas Print Name Print Name Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable. EJCDC® C -610, Performance Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 1 of 3 1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of the Construction Contract, which is incorporated herein by reference. 2. if the Contractor performs the Construction Contract, the Surety and the Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Paragraph 3. 3. if there is no Owner Default under the Construction Contract, the Surety's obligation under this Bond shall arise after: 3.1 The Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor, and Surety to discuss the Contractor's performance. if the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner's notice, request such a conference. If the Surety timely requests a conference, the Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Paragraph 3.1 shall be held within ten (10) business days of the Surety's receipt of the Owner's notice. if the Owner, the Contractor, and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner's right, if any, subsequently to declare a Contractor Default; 3.2 The Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and 33 The Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract. 4. Failure on the part of the Owner to comply with the notice requirement in Paragraph 3.1 shall not constitute a failure to comply with a condition precedent to the Surety's obligations, or release the Surety from its obligations, except to the extent the Surety demonstrates actual prejudice. 5. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety's expense take one of the following actions: 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract; 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors; 53 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and a contractor selected with the Owners concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 7 in excess of the Balance of the Contract Price incurred by the Owner as a result of the Contractor Default; or 5.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor, and with reasonable promptness under the circumstances: 5.4.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or 5.4.2 Deny liability in whole or in part and notify the Owner, citing the reasons for denial. 6. if the Surety does not proceed as provided in Paragraph 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Paragraph 5.4, and the Owner refuses the payment or the Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the Owner. 7. If the Surety elects to act under Paragraph 5.1, 5.2, or 5.3, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract Price, the Surety is obligated, without duplication for: 7.1 the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract; 7.2 additional legal, design professional, and delay costs resulting from the Contractor's Default, and resulting from the actions or failure to act of the Surety under Paragraph 5; and 7.3 liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non - performance of the Contractor. 8. If the Surety elects to act under Paragraph 5.1, 5.3, or 5.4, the Surety's liability is limited to the amount of this Bond. 9. The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors, and assigns. EJCDC® C -610, Performance Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 2 of 3 10. The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders, and other obligations. 11. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. if the provisions of this paragraph are void or prohibited by law, the minimum periods of limitations available to sureties as a defense in the jurisdiction of the suit shall be applicable. 12. Notice to the Surety, the Owner, or the Contractor shall be mailed or delivered to the address shown on the page on which their signature appears. 13. When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein, When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond. 14. Definitions 14.1 Balance of the Contract Price: The total amount payable by the Owner to the Contractor under the Construction Contract after all proper adjustments have been made including allowance for the Contractor for any amounts received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the Contractor under the Construction Contract. 14.2 Construction Contract: The agreement between the Owner and Contractor identified on the cover page, including all Contract Documents and changes made to the agreement and the Contract Documents, 14.3 Contractor Default: Failure of the Contractor, which has not been remedied or waived, to perform or otherwise to comply with a material term of the Construction Contract. 14.4 Owner Default: Failure of the Owner, which has not been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract. 14.5 Contract Documents: All the documents that comprise the agreement between the Owner and Contractor. 15. If this Bond is issued for an agreement between a contractor and subcontractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. 16. Modifications to this Bond areas follows: EJCDC® C -610, Performance Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 3 of 3 CORPORATE ACKNOWLEDGMENT State of Minnesota ) ) ss County of Wright ) On this l.S day of May 2017, before me appeared Philip B. Lesnar to me personally known, who, being by me duly sworn, did say that he /she is the President of Northdale Construction Company, Inc. , a corporation, and that said instrument was executed in behalf of said corporation by authority of its Board of Directors, and that said Philip B. Lesnar acknowledged said instrument to be the free act and deed of said corporation. Shelia J. Goeb s` NOTARY PUBLIC State of Minnesota My Commission Expires 1.31.20 State of Minnesota ) ) ss County of Hennepin ) Notary Public —W My commission expires SURETY ACKNOWLEDGMENT ldz�e� County, f� On this 11th day of May 2017 , before me appeared Rachel Thomas to me personally know, who being by me duly sworn, did say that (s)he is the Attorney -in -Fact of The Guarantee Company of North America USA , a corporation, that the seal affixed to the foregoing instrument is the corporate seal of said corporation and that said instrument was executed in behalf of said corporation by authority of its Board of Directors; and that said Rachel Thomas acknowledged said instrument to be the free act and deed of said corporation. LIN &...ILVEN POTPRYPUBl.1C -MINNESOTA Notary Public Ramsey County, Minnesota ' My Commission Expires ' Jai'!ua w 31, 2020 My commission expires 1/31/2020 k�.t, pare+; i�« v�4� ,. v. ,�v � .... a , �.� 1 0 yW,+t. � i� "R°b when, , , r . � .x.. Brian J. Oestreich, Joshua R. Loftis, R. Scott Egginton, R. W. Frank, John E. Tauer, Craig Remick, Rachel Thomas, Nicole Stillings, Jerome T. Ouimet, Kurt C. Lundbiad, Melinda C. Blodgett, R.C. Bowman, Ted Jorgensen, Emily Keiser Cobb Strecker Dunphy & Zimmermann, Inc. its true and lawful attorney(s) -in -fact to execute, seal and deliver for and on its behalf as surety, any and all bonds and undertakings, contracts of indemnity and other writings obligatory in the nature thereof, which are or may be allowed, required or permitted by law, statute, rule, regulation, contract or otherwise. The execution of such instrument(s) in pursuance of these presents, shall be as binding upon THE GUARANTEE COMPANY OF NORTH AMERICA USA as fully and amply, to all intents and purposes, as if the same had been duly executed and acknowledged by its regularly elected officers at the principal office. The Power of Attorney is executed and may be certified so, and may be revoked, pursuant to and by authority of Article IX, Section 9.03 of the By -Laws adopted by the Board of Directors of THE GUARANTEE COMPANY OF NORTH AMERICA USA at a meeting held on the 31 SI day of December, 2003. The President, or any Vice President, acting with any Secretary or Assistant Secretary, shall have power and authority: 1. To appoint Attorney(s) -in -fact, and to authorize them to execute on behalf of the Company, and attach the Seal of the Company thereto, bonds and undertakings, contracts of indemnity and other writings obligatory in the nature thereof; and 2. To revoke, at any time, any such Attorney -in -fact and revoke the authority given, except as provided below 3. In connection with obligations in favor of the Florida Department of Transportation only, it is agreed that the power and authority hereby given to the Attorney -in -Fact includes any and all consents for the release of retained percentages and /or final estimates on engineering and construction contracts required by the State of Florida Department of Transportation. It is fully understood that consenting to the State of Florida Department of Transportation making payment of the final estimate to the Contractor and /or its assignee, shall not relieve this surety company of any of its obligations under its bond. 4. In connection with obligations in favor of the Kentucky Department of Highways only, it is agreed that the power and authority hereby given to the Attorney -in -Fact cannot be modified or revoked unless prior written personal notice of such intent has been given to the Commissioner — Department of Highways of the Commonwealth of Kentucky at least thirty (30) days prior to the modification or revocation. Further, this Power of Attorney is signed and sealed by facsimile pursuant to resolution of the Board of Directors of the Company adopted at a meeting duly called and held on the 6th day of December 2011, of which the following is a true excerpt: RESOLVED that the signature of any authorized officer and the seal of the Company may be affixed by facsimile to any Power of Attorney or certification thereof authorizing the execution and delivery of any bond, undertaking, contracts of indemnity and other writings obligatory in the nature thereof, and such signature and seal when so used shall have the same force and effect as though manually affixed. IN WITNESS WHEREOF, THE GUARANTEE COMPANY OF NORTH AMERICA USA has caused this instrument to be signed and its corporate seal to be affixed by its authorized officer, this 2nd day of October, 2015. THE GUARANTEE COMPANY OF NORTH AMERICA USA R'7V AMER�P STATE OF MICHIGAN Stephen C. Ruschak, President & Chief Operating Officer Randall Musselman, Secretary County of Oakland On this 2nd day of October, 2015 before me came the individuals who executed the preceding instrument, to me personally known, and being by me duly sworn, said that each is the herein described and authorized officer of The Guarantee Company of North America USA; that the seal affixed to said instrument is the Corporate Seal of said Company; that the Corporate Seal and each signature were duly affixed by order of the Board of Directors of *% Cynthia A. Takai IN WITNESS WHEREOF, I have hereunto set my hand at The Guarantee Notary Public, State of Michigan Company of North America USA offices the day and year above written. County of Oakland My Commission Expires February 27, 2018 Acting in Oakland County 1, Randall Musselman, Secretary of THE GUARANTEE COMPANY OF NORTH AMERICA USA, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney executed by THE GUARANTEE COMPANY OF NORTH AMERICA USA, which is still in full force and effect. oy^ref�r IN WITNESS WHEREOF, I have thereunto set my hand and attached the seal of said Company this 11th day of May 2017 Randall Musselman, Secretary dfl" ENGINEERS JOINT CONTRACT f,0Ct1,%1ENTS CONUMITTEE CONTRACTOR (name and address): SURETY (name and address of principal place of business): Northdale Construction Company, Inc. The Guarantee Company of North America USA One Towne Square, Suite 1470 9760 71 st Street NE Southfield, MI 48076 -3725 Albertville, MN 55301 OWNER (name and address): City of Columbia Heights 637 38th Avenue N.E., Columbia Heights, MN 55421 CONSTRUCTION CONTRACT Effective Date of the Agreement: May 8, 2017 Amount: $393,924.72 Description (name and location): 2017 Water Main Construction - Project 1703 / 2017 Water Main Hydrant and Gate Valve Construction - Project 1710 BOND Bond Number: 16145092 Date (not earlier than the Effective Date of the Agreement of the Construction Contract): May 11, 2017 Amount: $393,924.72 Modifications to this Bond Form: ® None ❑ See Paragraph 18 Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Payment Bond to be duly executed by an authorized officer, agent, or representative. CONTRACTOR AS PRINCIPAL Northdale Construction Company, Inc. SURETY The Guarantee Company of North America USA (seal) (seal) Contractor' and Corporate Seal Surety's Name and Corporate Seal By:% '��� By: Signature Signature (attach power of attorney) Philip B. Lesnar Rachel Thomas Print Name Print Name Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable. EJCDC® C -615, Payment Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 1 of 3 6. If a notice of non - payment required by Paragraph 5.1.1 is 1. The Contractor and Surety, jointly and severally, bind given by the Owner to the Contractor, that is sufficient to themselves, their heirs, executors, administrators, satisfy a Claimant's obligation to furnish a written notice of successors, and assigns to the Owner to pay for labor, non - payment under Paragraph 5.1.1. materials, and equipment furnished for use in the performance of the Construction Contract, which is 7. When a Claimant has satisfied the conditions of Paragraph incorporated herein by reference, subject to the following 5.1 or 5.2, whichever is applicable, the Surety shall terms. promptly and at the Surety's expense take the following actions: 2. If the Contractor promptly makes payment of all sums due to Claimants, and defends, indemnifies, and holds 7.1 Send an answer to the Claimant, with a copy to the harmless the Owner from claims, demands, liens, or suits Owner, within sixty (60) days after receipt of the by any person or entity seeking payment for labor, Claim, stating the amounts that are undisputed and materials, or equipment furnished for use in the the basis for challenging any amounts that are performance of the Construction Contract, then the Surety disputed; and and the Contractor shall have no obligation under this Bond. 7.2 Pay or arrange for payment of any undisputed amounts. 3. if there is no Owner Default under the Construction Contract, the Surety's obligation to the Owner under this 7.3 The Surety's failure to discharge its obligations Bond shall arise after the Owner has promptly notified the under Paragraph 7.1 or 7.2 shall not be deemed to Contractor and the Surety (at the address described in constitute a waiver of defenses the Surety or Paragraph 13) of claims, demands, liens, or suits against Contractor may have or acquire as to a Claim, the Owner or the Owner's property by any person or except as to undisputed amounts for which the entity seeking payment for labor, materials, or equipment Surety and Claimant have reached agreement. If, furnished for use in the performance of the Construction however, the Surety fails to discharge its Contract, and tendered defense of such claims, demands, obligations under Paragraph 7.1 or 7.2, the Surety liens, or suits to the Contractor and the Surety. shall indemnify the Claimant for the reasonable attorney's fees the Claimant incurs thereafter to 4. When the Owner has satisfied the conditions in Paragraph recover any sums found to be due and owing to 3, the Surety shall promptly and at the Surety's expense the Claimant. defend, indemnify, and hold harmless the Owner against a duly tendered claim, demand, lien, or suit. 8. The Surety's total obligation shall not exceed the amount of this Bond, plus the amount of reasonable attorney's 5. The Surety's obligations to a Claimant under this Bond fees provided under Paragraph 7.3, and the amount of this shall arise after the following: Bond shall be credited for any payments made in good faith by the Surety. 5.1 Claimants who do not have a direct contract with the Contractor, 9. Amounts owed by the Owner to the Contractor under the Construction Contract shall be used for the performance 5.1.1 have furnished a written notice of non- of the Construction Contract and to satisfy claims, if any, payment to the Contractor, stating with under any construction performance bond. By the substantial accuracy the amount claimed Contractor furnishing and the Owner accepting this Bond, and the name of the party to whom the they agree that all funds earned by the Contractor in the materials were, or equipment was, performance of the Construction Contract are dedicated furnished or supplied or for whom the to satisfy obligations of the Contractor and Surety under labor was done or performed, within this Bond, subject to the Owner's priority to use the funds ninety (90) days after having last for the completion of the work. performed labor or last furnished materials or equipment included in the 10. The Surety shall not be liable to the Owner, Claimants, or Claim; and others for obligations of the Contractor that are unrelated to the Construction Contract. The Owner shall not be 5.1.2 have sent a Claim to the Surety (at the liable for the payment of any costs or expenses of any address described in Paragraph 13). Claimant under this Bond, and shall have under this Bond no obligation to make payments to or give notice on 5.2 Claimants who are employed by or have a direct behalf of Claimants, or otherwise have any obligations to contract with the Contractor have sent a Claim to Claimants under this Bond. the Surety (at the address described in Paragraph 13). 11. The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders, and other obligations. EJCDC® C -615, Payment Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 2 of 3 12. No suit or action shall be commenced by a Claimant under 8. The total amount due and unpaid to the this Bond other than in a court of competent jurisdiction in Claimant for labor, materials, or equipment the state in which the project that is the subject of the furnished as of the date of the Claim. Construction Contract is located or after the expiration of one year from the date (1) on which the Claimant sent a 16.2 Claimant: An individual or entity having a direct Claim to the Surety pursuant to Paragraph 5.1.2 or 5.2, or contract with the Contractor or with a (2) on which the last labor or service was performed by subcontractor of the Contractor to furnish labor, anyone or the last materials or equipment were furnished materials, or equipment for use in the performance by anyone under the Construction Contract, whichever of of the Construction Contract. The term Claimant (1) or (2) first occurs. If the provisions of this paragraph also includes any individual or entity that has are void or prohibited by law, the minimum period of rightfully asserted a claim under an applicable limitation available to sureties as a defense in the mechanic's lien or similar statute against the real jurisdiction of the suit shall be applicable. property upon which the Project is located, The intent of this Bond shall be to include without 13. Notice and Claims to the Surety, the Owner, or the limitation in the terms of "labor, materials, or Contractor shall be mailed or delivered to the address equipment" that part of the water, gas, power, shown on the page on which their signature appears. light, heat, oil, gasoline, telephone service, or Actual receipt of notice or Claims, however accomplished, rental equipment used in the Construction shall be sufficient compliance as of the date received. Contract, architectural and engineering services required for performance of the work of the 14. When this Bond has been furnished to comply with a Contractor and the Contractor's subcontractors, statutory or other legal requirement in the location where and all other items for which a mechanic's lien may the construction was to be performed, any provision in be asserted in the jurisdiction where the labor, this Bond conflicting with said statutory or legal materials, or equipment were furnished. requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal 16.3 Construction Contract: The agreement between requirement shall be deemed incorporated herein. When the Owner and Contractor identified on the cover so furnished, the intent is that this Bond shall be construed page, including all Contract Documents and all as a statutory bond and not as a common law bond. changes made to the agreement and the Contract Documents. 15. Upon requests by any person or entity appearing to be a potential beneficiary of this Bond, the Contractor and Owner shall promptly furnish a copy of this Bond or shall permit a copy to be made. 16. Definitions 16.1 Claim: A written statement by the Claimant including at a minimum: 1. The name of the Claimant; 2. The name of the person for whom the labor was done, or materials or equipment furnished; 3. A copy of the agreement or purchase order pursuant to which labor, materials, or equipment was furnished for use in the performance of the Construction Contract; 4. A brief description of the labor, materials, or equipment furnished; 5. The date on which the Claimant last performed labor or last furnished materials or equipment for use in the performance of the Construction Contract; 6. The total amount earned by the Claimant for labor, materials, or equipment furnished as of the date of the Claim; 7. The total amount of previous payments received by the Claimant; and 16.4 Owner Default: Failure of the Owner, which has not been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract. 16.5 Contract Documents: All the documents that comprise the agreement between the Owner and Contractor. 17. If this Bond is issued for an agreement between a contractor and subcontractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. 18. Modifications to this Bond are as follows: EJCDCa C -615, Payment Bond Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 3 of 3 CORPORATE ACKNOWLEDGMENT State of Minnesota ) ) ss County of Wright ) On this Z6— day of May 2017, before me appeared Philip B. Lesnar to me personally known, who, being by me duly sworn, did say that he /she is the President of Northdale Construction Company, Inc. , a corporation, and that said instrument was executed in behalf of said corporation by authority of its Board of Directors, and that said Philip B. Lesnar said corporation. Sheila J. Goeb <, Y NOTARY PUBLIC State of Minnesota My Commission Expires 1.31.2020 State of Minnesota ) ) ss County of Hennepin ) acknowledged said instrument to be the free act and deed of Notary Public h County, A411 My commission expires /� SURETY ACKNOWLEDGMENT On this 11th day of May 1 2017 , before me appeared Rachel Thomas , to me personally know, who being by me duly sworn, did say that (s)he is the Attorney -in -Fact of The Guarantee Company of North America USA , a corporation, that the seal affixed to the foregoing instrument is the corporate seal of said corporation and that said instrument was executed in behalf of said corporation by authority of its Board of Directors; and that said Rachel Thomas acknowledged said instrument to be the free act and deed of said corporation. f, NOTARY PUBLIC - MINNESOTA My Commission Expires January 31, 2020 Notary Public Ramsey County, Minnesota My commission expires 1/31/2020 _. ,. ni`,, H.��s Brian J. Oestreich, Joshua R. Loftis, R. Scott Egginton, R. W. Frank, John E. Tauer, Craig Remick, Rachel Thomas, Nicole Stillings, Jerome T. Ouimet, Kurt C. Lundblad, Melinda C. Blodgett, R.C. Bowman, Ted Jorgensen, Emily Keiser Cobb Strecker Dunphy & Zimmermann, Inc. its true and lawful attorney(s) -in -fact to execute, seal and deliver for and on its behalf as surety, any and all bonds and undertakings, contracts of indemnity and other writings obligatory in the nature thereof, which are or may be allowed, required or permitted by law, statute, rule, regulation, contract or otherwise. The execution of such instrument(s) in pursuance of these presents, shall be as binding upon THE GUARANTEE COMPANY OF NORTH AMERICA USA as fully and amply, to all intents and purposes, as if the same had been duly executed and acknowledged by its regularly elected officers at the principal office. The Power of Attorney is executed and may be certified so, and may be revoked, pursuant to and by authority of Article IX, Section 9.03 of the By -Laws adopted by the Board of Directors of THE GUARANTEE COMPANY OF NORTH AMERICA USA at a meeting held on the 31" day of December, 2003. The President, or any Vice President, acting with any Secretary or Assistant Secretary, shall have power and authority: 1. To appoint Attorney(s) -in -fact, and to authorize them to execute on behalf of the Company, and attach the Seal of the Company thereto, bonds and undertakings, contracts of indemnity and other writings obligatory in the nature thereof; and 2. To revoke, at any time, any such Attorney -in -fact and revoke the authority given, except as provided below 3. In connection with obligations in favor of the Florida Department of Transportation only, it is agreed that the power and authority hereby given to the Attorney -in -Fact includes any and all consents for the release of retained percentages and /or final estimates on engineering and construction contracts required by the State of Florida Department of Transportation. It is fully understood that consenting to the State of Florida Department of Transportation making payment of the final estimate to the Contractor and /or its assignee, shall not relieve this surety company of any of its obligations under its bond. 4. In connection with obligations in favor of the Kentucky Department of Highways only, it is agreed that the power and authority hereby given to the Attorney -in -Fact cannot be modified or revoked unless prior written personal notice of such intent has been given to the Commissioner — Department of Highways of the Commonwealth of Kentucky at least thirty (30) days prior to the modification or revocation. Further, this Power of Attorney is signed and sealed by facsimile pursuant to resolution of the Board of Directors of the Company adopted at a meeting duly called and held on the 6th day of December 2011, of which the following is a true excerpt: RESOLVED that the signature of any authorized officer and the seal of the Company may be affixed by facsimile to any Power of Attorney or certification thereof authorizing the execution and delivery of any bond, undertaking, contracts of indemnity and other writings obligatory in the nature thereof, and such signature and seal when so used shall have the same force and effect as though manually affixed. OA. � " IN WITNESS WHEREOF, THE GUARANTEE COMPANY OF NORTH AMERICA USA has caused this instrument to be signed and aw its corporate seal to be affixed by its authorized officer, this 2 "a day of October, 2015. % �� THE GUARANTEE COMPANY OF NORTH AMERICA USA P STATE OF MICHIGAN Stephen C. Ruschak, President & Chief Operating Officer Randall Musselman, Secretary County of Oakland On this 2nd day of October, 2015 before me came the individuals who executed the preceding instrument, to me personally known, and being by me duly sworn, said that each is the herein described and authorized officer of The Guarantee Company of North America USA; that the seal affixed to said instrument is the Corporate Seal of said Company; that the Corporate Seal and each signature were duly affixed by order of the Board of Directors of fk Cynthia A. Takai IN WITNESS WHEREOF, I have hereunto set my hand at The Guarantee Notary Public, State of Michigan Company of North America USA offices the day and year above written. County of Oakland My Commission Expires February 27, 2018 Acting in Oakland County I, Randall Musselman, Secretary of THE GUARANTEE COMPANY OF NORTH AMERICA USA, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney executed by THE GUARANTEE COMPANY OF NORTH AMERICA USA, which is still in full force and effect. QJryr�+=FeC IN WITNESS WHEREOF, I have thereunto set my hand and attached the seal of said Company this 11th day of May 2017 0C t1fAMER P Randall Musselman, Secretary ACC>Rbr CERTIFICATE OF LIABILITY ' S ie DATE (MMIDDIYYYY) CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, 5/11/2017 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER Certificates Department X NAME: PHONE (952)707 -8200 AIC No: (952) 890 -0535 Kraus - Anderson Insurance E -MAIL ADDRESS: certificates @kainsurance.com 420 Gateway Boulevard INSURERS AFFORDING COVERAGE NAIC # $ 1,000,000 INSURER A:Amer].sure Insurance Company DAMAGE TO RENTED PREMISES Ea occurrence Burnsville MN 55337 -2790 INSURED INSURER B: $ 10,000 Northdale Construction Co. Inc INSURERC: X 9760 71st Street NE INSURER D: 4/1/2017 INSURER E INSURER F: $ 1,000,000 Albertville MN 55301 COVERAGES CERTIFICATE NUMBER :17 -18 Certificate REVISION NUMBER- THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR LTR TYPE OF INSURANCE ADDL SUBR _tUll POLICY NUMBER POLICY EFF MM /DD [YYYY1 POLICY EXP (MMIDDIYYYY1 LIMITS A X COMMERCIAL GENERAL LIABILITY CLAIMS -MADE [XI OCCUR EACH OCCURRENCE $ 1,000,000 DAMAGE TO RENTED PREMISES Ea occurrence $ 1,000,000 MED EXP (Any one person) $ 10,000 X CPP 20964470301 4/1/2017 4/1/2018 PERSONAL & ADV INJURY $ 1,000,000 GEN'L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 2,000,000 POLICY II PE� I LOC PRODUCTS - COMP /OP AGG $ 2,000,000 $ OTHER: AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT Ea accident $ 1,000,000 BODILY INJURY (Per person) $ A X ANY AUTO ALL OWNED SCHEDULED AUTOS AUTOS X CA20964460101 4/1/2017 4/1/2018 BODILY INJURY Per accident) $ HIRED AUTOS NON -OWNED AUTOS PROPERTY DAMAGE Per accident $ X UMBRELLA LIAB I X OCCUR EACH OCCURRENCE $ 5,000,000 AGGREGATE $ 5,000,000 A EXCESS LIAB CLAIMS -MADE DED I X I RETENTION$ 0 $ X CU 20964480202 4/1/2017 4/1/2018 WORKERS COMPENSATION AND EMPLOYERS' LIABILITY YIN X PER OTH- STATUTE I ER E.L. EACH ACCIDENT $ 1,000,000 A ANY PROPRIETOR/PARTNER /EXECUTIVE OFFICER /MEMBER EXCLUDED? N❑ (Mandatory in NH) NIA WC 21004970101 4/1/2017 4/1/2018 E.L. DISEASE - EA EMPLOYE ' $ 1,000,000 If yes, describe under DESCRIPTION OF OPERATIONS below E.L. DISEASE - POLICY LIMIT 1 $ 1,000,000 DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required) RE: 2017 Water Main Construction & 2017 Hydrant & Gate Valve Construction. ** *SEE ATTACHED * ** (763)706 -3701 khansen @columbiaheightsmn. City of Columbia Heights 637 38th Avenue NE Columbia Heights, MN 55421 ACORD 25 (2014/01) INS025 (201401) SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE tt Broderson /MARIEL _ ©1988 -2014 ACORD CORPORATION. All rights reserved. The ACORD name and logo are registered marks of ACORD THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. CONTRACTOR'S BLANKET ADDITIONAL i ENDORSEMENT FORM A This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART Policy Number CPP20964470301 Agency Number 0245002 Policy Effective Date 04/01/2017 Policy Expiration Date Date Account Number 04/01/2018 04/05/2017 20063919 Named Insured Agency Issuing Company NORTHDALE CONSTRUCTION CO., KRAUS- ANDERSON INSURANCE, AMERISURE INSURANCE INC ET AL COMPANY 1. a. SECTION 11 - WHO IS AN INSURED is amended to add as an additional insured any person or organization: (1) Whom you are required to add as an additional insured on this policy under a written contract or written agreement relating to your business; or (2) Who is named as an additional insured under this policy on a certificate of insurance. b. The written contract, written agreement, or certificate of insurance must: (1) Require additional insured status for a time period during the term of this policy; and (2) Be executed prior to the "bodily injury", "property damage ", or "personal and advertising injury" leading to a claim under this policy. c. If, however: (1) "Your work" began under a letter of intent or work order; and (2) The letter of intent or work order led to a written contract or written agreement within 30 days of beginning such work; and (3) Your customer's customary contracts require persons or organizations to be named as additional insureds; we will provide additional insured status as specified in this endorsement. 2. The insurance provided under this endorsement is limited as follows: a. That person or organization is an additional insured only with respect to liability caused, in whole or in part, by: (1) Premises you: (a) Own; (b) Rent; (c) Lease; or (d) Occupy; (2) Ongoing operations performed by you or on your behalf. Ongoing operations does not apply to "bodily injury" or "property damage" occurring after: Includes copyrighted material of Insurance Services Office, Inc. CG 70 48 18 15 Pages 1 c44 (a) All work to be performed by you or on your behalf for the additional insured(s) at the site of the covered operations is complete, including related materials, parts or equipment (other than service, maintenance or repairs); or (b) That portion of "your work" out of which the injury or damage arises is put to its intended use by any person or organization other than another contractor working for a principal as a part of the same project. (3) Completed operations coverage, but only if: (a) The written contract, written agreement, or certificate of insurance requires completed operations coverage or "your work" coverage; and (b) This coverage part provides coverage for "bodily injury" or "property damage" included within the "products- completed operations hazard ". However, the insurance afforded to such additional insured only applies to the extent permitted by law. b. If the written contract, written agreement, or certificate of insurance: (1) Requires "arising out of language; or (2) Requires you to provide additional insured coverage to that person or organization by the use of either or both of the following: (a) Additional Insured — Owners, Lessees or Contractors — Scheduled Person Or Organization endorsement CG 20 10 10 01: or (b) Additional Insured — Owners, Lessees or Contractors — Completed Operations endorsement CG 20 37 10 01; then the phrase "caused, in whole or in part, by" in paragraph 2.a. above is replaced by "arising out of'. c. If the written contract, written agreement, or certificate of insurance requires you to provide additional insured coverage to that person or organization by the use of: (1) Additional Insured — Owners, Lessees or Contractors — Scheduled Person Or Organization endorsement CG 20 10 07 04 or CG 20 10 04 13; or (2) Additional Insured — Owners, Lessees or Contractors — Completed Operations endorsement CG 20 37 07 04 or CG 20 37 04 13; or (3) Both those endorsements with either of those edition dates; or (4) Either or both of the following: (a) Additional Insured — Owners, Lessees or Contractors — Scheduled Person Or Organization endorsement CG 20 10 without an edition date specified; or (b) Additional Insured —Owners, Lessees or Contractors —Completed Operations endorsement CG 20 37 without an edition date specified; then paragraph 2.a. above applies. d. Premises, as respects paragraph 2.a.(1) above, include common or public areas about such premises if so required in the written contract or written agreement. e. Additional insured status provided under paragraphs 2.a.(1)(b) or 2.a.(1)(c) above does not extend beyond the end of a premises lease or rental agreement. f. 1 he limits of insurance that apply to the additional insured are the least of those specified in the: (1) Written contract; (2) Written agreement; (3) Certificate of insurance: or (4) Declarations of this policy. The limits of insurance are inclusive of and not in addition to the limits of insurance shown in the Declarations. Includes copyrighted material of Insurance Services Office, Inc. Page 2 of 4 CG 70 4810 15 g. The insurance provided to the additional insured does not apply to "bodily injury", "property damage ", or "personal and advertising injury" arising out of an architect's, engineer's, or surveyor's rendering of, or failure to render, any professional services, including but not limited to: (1) The preparing, approving, or failing to prepare or approve: (a) Maps; (b) Drawings; (c) Opinions; (d) Reports; (e) Surveys; (f) Change orders; (g) Design specifications; and (2) Supervisory, inspection, or engineering services. h. SECTION IV— COMMERCIAL GENERAL LIABILITY CONDITIONS, paragraph 4. Other Insurance is deleted and replaced with the following: 4. Other Insurance. Coverage provided by this endorsement is excess over any other valid and collectible insurance available to the additional insured whether: a. Primary; b. Excess; c. Contingent; or d. On any other basis; but if the written contract, written agreement, or certificate of insurance requires primary and non- contributory coverage, this insurance will be primary and non - contributory relative to other insurance available to the additional insured which covers that person or organization as a Named Insured, and we will not share with that other insurance. L If the written contract, written agreement, or certificate of insurance as outlined above requires additional insured status by use of CG 20 10 11 85, then the coverage provided under this CG 70 48 endorsement does not apply except for paragraph 2.h. Other Insurance. Additional insured status is limited to that provided by CG 20 10 11 85 shown below and paragraph 2.h. Other Insurance shown above. ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS (FORM B) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART. SCHEDULE Name of Person or Organization: Blanket Where Required by Written Contract, Agreement, or Certificate of Insurance that the terms of CG 20 10 11 85 apply (if no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) WHO IS AN INSURED (Section 11) is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of "your work" for that insured by or for you. CG 2010 1185 Copyright, Insurance Services Office, Inc., 1984 Includes copyrighted material of Insurance Services Office, Inc. CG 70 48 10 15 Pages 3 of 4 j, The insurance provided by this endorsement does not apply to any premises or work for which the person or organization is specifically listed as an additional insured on another endorsement attached to this policy. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 4 CG 70 48 1015