RE: DNR Water Supply Plan
Columbia Heights, MN
Estimate of Engineering Fees
Dear Mr. Hansen:
v ~v ✓41Y.V V v Suite 206
Ramsey, MN 55303 -5119
Ph: (763) 433-2851
Fax: (763) 427-0833
Bolton- Menk.com
We appreciate the opportunity to assist the City of Columbia Heights with completion of the Water
Supply Plan as required by the Minnesota Department of Natural Resources (DNR).
PROTECT UNDERSTANDING
Minnesota State Statute requires all public water supply systems serving more than 1,000 people and/or
all cities in the seven - county metropolitan area, must have a water supply plan approved by the DNR.
Water supply plans must be updated and submitted to the DNR for approval every ten years. This
requirement, in place since the 1990s, is designed to encourage communities to deal proactively with
providing sustainable drinking water for citizens, businesses, and industry. To meet this requirement, the
DNR is requiring that a Water Supply Plan for the City of Columbia Heights be completed by December
31, 2016.
SCOPE OF WORK
The DNR has developed a standard template for Water Supply Plans and instructions for completion of
the plan. The scope of work will include completing the plan template as required to gain approval of the
plan from the DNR. Part 2 and Part 3 will require a meeting between Bolton & Menk and appropriate
City staff to assist in developing procedures and conservation measures that meet the City's goals and
expectations.
Specific tasks required to complete the plan are as follows:
• Project kick -off meeting (completed),
• Collection of data (City collects data and transmits to Bolton & Menk),
• Evaluation of data to complete the requirements of the plan,
C:\ Users \kevinki \Desktop \Water Supply Plan Proposal CH 112116.docx
Mr. Kevin Hansen, P.E.
November 21, 2016
Page: 2
• Completion of the Water Supply Plan Template:
• Part 1 — Water Supply System Description and Evaluation
• Part 2 — Emergency Planning and Response Procedures
o Part 3 — Water Conservation Plan
o Part 4 — Metro Area Water Suppliers
• Up to 1 additional meeting with DNR and /or City staff,
• City review of draft plan,
• Submittal of draft plan to DNR and the Metropolitan Council for approval,
• Preparation of resolution for City Council adoption of approved plan, and
• Final completion of plan for submittal prior to December 31, 2016.
PROJECT FEES
Bolton & Menk, Inc. proposes to provide engineering services for completion of the DNR Water Supply
Plan as listed above for a not -to- exceed fee of $9,200.
We look forward to assisting you with this project and we appreciate the City's continued consideration
of Bolton & Menk, Inc. If you need any additional information or have any questions on the above please
do not hesitate to give me a call at 651-968-7760.
Respectfully Submitted,
Bolton & Menk, Inc.
' _.
Kevin Kielb, P.E.
Client Services Manager
Accepted /Authorized By:
C: \Users \kevinki \Desktop \Water Supply Plan Proposal CH 112116.docx
y-
Paul Saffert, P.E.
Project Manager