January 31, 2001
Mr. Kevin Hansen, PE
Public Works Director\ City Engineer
City of Columbia Heights
637 - 38 Avenue N.E.
Columbia Heights, MN 55421
RE: Proposal for Additional Final Design Services
Central Avenue (TH 65) Improvement Project
City Project No. 99 -12
Dear Mr. Hansen:
The following supplemental proposal is offered for your consideration for additional final design
phase services for the above - referenced project. The additional services have been specifically
requested by City staff and are outside of the scope of work included in our January 10, 2000
proposal, our September 14, 2000 supplemental proposal for landscape design services and our
December 12, 2000 supplemental proposal.
SCOPE OF WORK
URS/BRW will provide additional final design phase services related to Right of Way for the
project as follows:
URS /BRW has reviewed the plans to determine the Right of Way required for
construction of the project. MnDOT is requiring that Right of Way be acquired for all
areas where the construction limits are shown outside of existing Rights of Way or
easements. We have analyzed the areas of encroachment with City staff and have
reduced the areas where Right of Way or easements will be required. We will modify
plan sheets in some areas to eliminate the need for Right of Way, however, in some areas
this can not be accomplished. Right of Way and/or easement acquisition will be required
for six properties. The plans are being revised for approximately thirteen other areas to
avoid the need for acquisitions.
Thresher Square
700 Third Street South
Minneapolis, MN 55415
612.370.0700 Tel
612.370.1378 Fax
Mr. Kevin Hansen
URS January 31, 200•
Page 2
BRW, Inc.
There are six properties requiring Right of Way and/or easement acquisitions for the
project, including the City Park located south of Bobby and Steve's. The properties are
identified below:
1. Columbia Heights Mall/Transit Hub
2. Columbia Park Clinic/Rapid Graphics Property
3. Columbia Heights Business Center
4. :Burger King
5. Mady's Bowling
6. City Park property south of Bobby and Steve's
Additional services are required for the plan revisions, as well as for the Right of Way
related services. The proposed Right of Way related services include preparation of
Right of Way /easement documents and descriptions and exhibits. We anticipate that one
meeting per property will be required either with City staff, the City Attorney and/or
property owners.
ESTIMATED COSTS
BRW will perform these additional services on an hourly basis consistent with our original
proposal and our Professional Services Agreement. The following is a summary of the estimated
costs to complete the work tasks detailed above.
Current Not -to- Exceed Amount $247,100.00
Additional Services $ 15,500.00
Revised Not -to- Exceed Amount $262,600.00
The total revised not -to- exceed cost for the design phase cost for this project is, therefore,
$262,600.00 including the additional services detailed in this supplemental proposal. Consistent
with our Professional Services Agreement, labor will be billed on an hourly basis using our
Standard Rate Schedule and reimbursable expenses will be billed to the City at cost with no
URS/BRW markup.
We have included exhibits depicting the parcels that easements and/or Right of Way is required
for the project for your review.
Two original copies of this proposal are enclosed. If the proposal is acceptable, please execute
both copies on the signature blocks provided below and return one copy to us for our records.
Mr. Kevin Hansen
URS January 31, 2001
Page 3
BRW, Inc.
Please let me know if you have any questions or you need any additional information.
Sincerely,
BRW, Inc.
Jo PE
r ice President
APPROVED BY:
CITY OF COLUMBIA HEIGHTS
Name Walter Fehst Name ipary Peterson
City Manager Mayor
Title Title
Signature Signature
Date Date
Copy: Kevin Kielb/BRW
Kim Schaffer /BRW
File 33910 - 004 -1001
URS RECEIVED
DEC 13200D
B RW ' � PUBLIC WORKS
December 12, 2000
Mr. Kevin Hansen, PE
Public Works Director\ City Engineer
City of Columbia Heights
637 - 38 Avenue N.E.
Columbia Heights, MN 55421
RE: Proposal for Additional Final Design Services
Central Avenue (TH 65) Improvement Project
City Project No. 99 -12
Dear Mr. Hansen:
The following supplemental proposal is offered for your consideration for additional final design
phase services for the above - referenced project. These additional services have been required for
the completion of the project plans and specifications or have been specifically requested by City
staff and are outside of the scope of work included in our January 10, 2000 proposal and our
September 14, 2000 supplemental proposal for landscape design services.
The scope of work and an estimated cost for these additional services are detailed below. We
have also provided an updated schedule for the project.
SCOPE OF WORK
URS/BRW will provide additional final design phase services for the project as follows.
1. Extension of Project from 43 Avenue to 45 Avenue
The project originally included improvements to Central Avenue between 37 Avenue
and 43 Avenue. Mn/DOT requested that the project limits be extended to include a
bituminous overlay between 43" Avenue and 45 Avenue. URSBRW will provide
additional services to include the preparation of final plans and specifications for the
overlay construction. We will also coordinate with Mn/DOT to define the scope of the
overlay work and negotiate with Mn/DOT to determine the additional funding that would
be available for the additional work.
Thresher Square
700 Third Street South
Minneapolis, MN 55415
612.370.0700 Tel
612.370.1378 Fax
Mr. Kevin Hansen
URS December 12, 2000
Page 2
BRW, Inc.
2. Utility Trench Pavement Design
The Feasibility Study for the project included the patching of all utility trenches with a
bituminous pavement section. The existing Central Avenue pavement section includes
approximately 2" to 6" of bituminous pavement over 6" to 9" of concrete pavement.
URS /BRW conducted discussions with Mn/DOT staff as a part of determining the final
pavement section for the roadway. Mn/DOT requested that all utility trenches be patched
in -kind with a bituminous overlay over new concrete pavement. We performed
additional analysis and subcontracted with a geotechnical subconsultant (American
Engineering Testing) to document that the bituminous pavement section option would
perform satisfactorily; however, Mn/DOT still required the bituminous overlay /concrete
pavement design.
As a result of this decision by Mn/DOT, additional final design phase services are
required to design the bituminous overlay and concrete pavement section. These
additional services will include the preparation of concrete pavement jointing plans,
details and specifications. This decision by Mn/DOT resulted in the addition of
approximately $150,000 to the project construction costs.
3. Additional Traffic Control /Staging Services
URS/BRW has conducted discussions with the Mn/DOT Traffic Office regarding the
traffic control and staging required for the project. It has been determined that the project
must be constructed under traffic and that traffic signal operation and left turn lanes must
be maintained at all intersections along Central Avenue. URS/BRW is preparing traffic
control and staging plans to detail the traffic control required for the project. Additional
services, including the preparation of plans and specifications detailing temporary signal
operations at each intersection for each phase of the project, are required as a result of
these discussions with Mn/DOT.
4. Preparation of Funding/Financing Alternatives
URS/BRW prepared detailed cost estimates as a part of our original scope of work for the
project. In addition to this work, we have also provided services associated with the
preparation of a financing plan for the project.
URS/BRW has also prepared assessment options related to the urban design
enhancements. This information was subsequently utilized to prepare the financing plan
for the project. This work is outside of the scope of our original agreement and the
supplemental agreement.
Mr. Kevin Hansen
URS December 12, 2000
Page 3
BRW, Inc.
5. Staff Requested Additions to the Project Scope/Revisions to Plans
Throughout the course of final design, URS/BRW has been requested to make
adjustments to the final design. The requests resulted from review meetings with City
staff. The revisions have included separation of storm sewer and sanitary sewer near 37
Avenue, grading revisions to the gutter line at 45 Avenue, watermain replacement at
Gould Avenue, the installation of a frost -free hydrant, revisions to the design of
Reservoir Boulevard, and revisions associated with business parking and access issues.
Additional miscellaneous services will be required to coordinate meetings with the MTC
and determine relocated bus stop locations.
6. Additional Public Involvement
URSBRW has provided preliminary design graphics/boards for presentation at an Open
House meeting and at a City Council worksession. The graphics detailed the proposed
urban design improvements and the proposed roadway layout and traffic control /staging
plans. We will also provide additional public involvement services including preparation
for and attendance at up to ten public or individual business owner meetings. The need
for these additional meetings has been determined based upon the public involvement
work performed to date.
We have not included any additional services associated with coordination of the project with the
City of Minneapolis. It is possible that the scope of the project may be modified to include the
replacement of the existing signal at the 37 Avenue intersection and to extend the limits of the
project to the south into the City of Minneapolis. We have not included these services at this
time since it is uncertain if this work will be added to the project. We propose that a separate
supplemental proposal be submitted for your consideration if this work is added to the project.
ESTIMATED COSTS
BRW will perform these additional services on an hourly basis consistent with our original
proposal and our Professional Services Agreement. The following is a summary of the estimated
costs to complete the work tasks detailed above.
Current Not -to- Exceed Amount $164,000.00
Additional Services
1. Extension of Project from 43 Ave. to 45 Ave. $16,000.00
2. Utility Trench Pavement Design $17,500.00
3. Additional Traffic Control /Staging Services $16,000.00
4. Funding/Financing Alternatives $12,200.00
5. Staff Requested Additions/Revisions $13,400.00
Mr. Kevin Hansen
URS December 12, 2000
Page 4
BRW, Inc.
6. Additional Public Involvement $ 8,000.00
Total Additional Services $ 83,100.00
Revised Not -to- Exceed Amount $247,100.00
The total revised not -to- exceed cost for the design phase cost for this project is, therefore,
$247,100.00 including the additional services detailed in this supplemental proposal. Consistent
with our Professional Services Agreement, labor will be billed on an hourly basis using our
Standard Rate Schedule and reimbursable expenses will be billed to the City at cost with no
URS/BRW markup.
SCHEDULE
The following is an updated schedule for the project:
Preliminary Plans Submitted to Mn/DOT for Review November 2000
Approve Cooperative Agreement/Plans & Specs February/March 2001
Bid Opening March/April 2001
Award Contract April/May 2001
Start Construction May 2001
Construction Complete November 2001
The project schedule is dependent upon the Mn/DOT Cooperative Agreement review process.
The schedule detailed above may need to be modified based upon the review process.
Two original copies of this proposal are enclosed. If the proposal is acceptable, please execute
both copies on the signature blocks provided below and return one copy to us for our records.
Please let me know if you have any questions or you need any additional information.
Sincerely,
BRW, Inc.
• n :. Horn, PE
Vice President
Mr. Kevin Hansen
URS December 12, 2000
Page 5
BRW, Inc.
APPROVED BY:
CITY OF COLUMBIA HEIGHTS /
/0 -111/
Walt Fehst :�A WP—
- S�
e Name Nam
City Manager • a or —
Title Title y
<4# ir,(41 41 111/1 A., give LA--
Si ignature
/.?-7(4 / — 2- -- 1
Date Date
Copy: Kevin Kielb/BRW
Kim Schaffer /BRW
File 33910 - 004 -1001