HomeMy WebLinkAboutContract 2302EJCDC
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF STIPULATED PRICE
2302
THIS AGREEMENT is by and between the CITY OF COLUMBIA HEIGHTS,
MINNESOTA (OWNER) and ELLINGSON DRAINAGE, INC.
(CONTRACTOR).
OWNER and CONTRACTOR, hereby agree as follows
ARTICLE 1-WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Work is generally described as follows:
2010 TRUNK SANITARY SEWER PIPE BURSTING
ARTICLE 2 -THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only
a part is generally described as follows:
CITY PROJECT N®. a~l~
PIPE BURSTING
• SANITARY SEWER BYPASS
• CONNECT SERVICES
• REMOVE AND REPLACE AS SPECIFIED
• RESTORATION
ARTICLE 3 -ENGINEER
3.01 The Project has been designed by the CITY OF COLUMBIA HEIGHTS'
ENGINEERING DEPARTMENT (ENGINEER), who is to act as OWNER's representative,
assume all duties and responsibilities, and have the rights and authority assigned to ENGINEER
in the Contract Documents in connection with the completion of the Work in accordance with
the Contract Documents.
ARTICLE 4 -CONTRACT TIMES
4.01 Time of the Essence
IS
A. All time limits for Milestones, if any, Substantial Completion, and completion
and readiness for final payment as stated in the Contract Documents are of the
essence of the Contract.
4.02 Dates for Substantial Completion and Final Payment
A. The Work will be substantially completed on or before September 30, 2010,
and completed and ready for final payment in accordance with Paragraph 14.07 of the
General Conditions on or before October 31.2010.
4.03 Liquidated Damages
A. CONTRACTOR and OWNER recognize that time is of the essence as stated in
Paragraph 4.01 above and that OWNER will suffer financial loss if the Work is not
completed within the times specified in Paragraph 4.02 above, plus any extensions
thereof allowed in accordance with Article 12 of the General Conditions. The parties
also recognize the delays, expense, and difficulties involved in proving in a legal or
arbitration proceeding the actual loss suffered by OWNER if the Work is not
completed on time. Accordingly, instead of requiring any such proof, OWNER and
CONTRACTOR agree that as liquidated damages for delay (but not as a penalty),
CONTRACTOR shall pay OWNER $250.00 for each day that expires after the time
specified in Paragraph 4.02 above for Substantial Completion until the Work is
substantially complete. After Substantial Completion, if CONTRACTOR shall
neglect, refuse, or fail to complete the remaining Work within the Contract Time or
any proper extension thereof granted by OWNER, CON1'RAC 1 OR shall pay
OWNER $250.00 for each day that expires after the time specified in Paragraph 4.02
above for completion and readiness for final payment until the Work is completed
and ready for final payment.
In addition, instead of requiring any such proof, OWNER and CONTRACTOR agree
that as liquidated damages far delay (but not as a penalty},CONTRACTOR shall pay
O ER $250.00 for each day that expires after the following milestones: N/A
ARTICLE 5 -CONTRACT PRICE
5.01 OWNER shall pay CONTRACTOR far completion of the Work in accordance with.
the Contract Documents an amount in current funds equal to the sum of the amounts
determined pursuant to paragraphs below:
For all Work, at the prices stated in CONTRACTOR'S Bid, attached hereto as
Exhibit A.
As provided in Paragraph 11.03 of the General Conditions, estimated quantities are
not guaranteed, and determinations of actual quantities and classifications are to be
made by ENGINEER as provided in Paragraph 9.07 of the General Conditions. Unit
prices have been computed as provided in Paragraph 11.03 of the General
Conditions.
19
ARTICLE 6 -PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. CONTRACTOR shall submit Applications for Payment in accordance with
Article 14 of the General Conditions. Applications for Payment will be processed by
ENGINEER as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. OWNER shall make progress payments on account of the Contract Price on
the basis of CONTRACTOR's Applications for Payment on or about the fifteenth
day of each month during performance of the Work as provided in Paragraphs
6.02.A.1 and 6.02.A.2 below. All such payments will be measured by the schedule
of values established as provided in Paragraph 2.07.A of the General Conditions (and
in the case of Unit Price Work based on the number of units completed) or, in the
event there is no schedule of values, as provided in the General Requirements.
1. Prior to Substantial Completion, progress payments will be made in
an amount equal to the percentage indicated below but, in each case, less the
aggregate of payments previously made and less such amounts as
ENGINEER may determine or OWNER may withhold including but not
limited to liquidated damages, in accordance with Paragraph 14.02 of the
General Conditions:
a. 95% of Work completed (with the balance being retainage). If
the Work has been 50% completed as determined by ENGINEER,
and if the character and progress of the Work have been satisfactory
to OWNER and ENGINEER, OWNER, on recommendation of
ENGINEER, may determine that as long as the character and progress
of the Work remain satisfactory to theirs, there will be no additional
re~~rnage; and
b. 95% of cost of materials and equipment not incorporated in
the Work (with the balance being retainage}.
2. Upon Substantial Completion, OWNER shall pay an amount
sufficient to increase total payments to CONTRACTOR to 98% of the Work
completed, less such amounts as ENGINEER shall. determine in accordance
with Paragraph 14.02.B.5 of the General Conditions and less 5% of
ENGINEER's estimate of the value of Work to be completed or corrected as
shown on the tentative list of items to be completed or corrected attached to the
certificate of Substantial Completion.
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with
Paragraph 14.07 of the General Conditions, OWNER shall pay the remainder of the
Contract Price as recommended by ENGINEER as provided in said Paragraph 14.07.
20
ARTICLE 7 -INTEREST
7.01 All moneys not paid when due as provided in Article 14 of the General Conditions
shall bear interest at the rate stipulated in Minnesota Statute 161.322.
ARTICLE 8 -CONTRACTOR'S REPRESENTATIONS
8.01 In order to induce OWNER to enter this Agreement CONTRACTOR makes the
following representations:
A. CONTRACTOR has examined and carefully studied the Contract Documents
and the other related data identified in the Bidding Documents.
B. CONTRACTOR has visited the Site and become familiar with and is satisfied
as to the general, local, and Site conditions that may affect cost, progress, and
performance of the Work.
C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and
local Laws and Regulations that may affect cost, progress, and performance of the
Work.
D. CONTRACTOR has carefully studied all : (1) reports of explorations and tests
of subsurface conditions at or contiguous to the Site and all drawings of physical
conditions in or relating to existing surface or subsurface structures at or contiguous
to the Site (except Underground Facilities) which have been identified in the
Supplementary Conditions as provided in Paragraph 4.02 of the General Conditions
and (2) reports and drawings of a Hazardous Environmental Condition, ifany, at the
Site which has been identified in the Supplementary Conditions as provided ire
Paragraph 4.06 of the General Conditions.
E. CONT CTOR has obtained and carefully studied (or assumes
responsibility for doing so) all additional or supplementary examinations,
investigations, explorations, tests, studies, and data concerning conditions (surface,
subsurface, and Underground Facilities) at or contiguous to the Site which may affect
cost, progress, or performance of the Work or which relate to any aspect of the
means, methods, techniques, sequences, and procedures of construction to be
employed by CONTRACTOR, including any specific means, methods, techniques,
sequences, and procedures of canstruction expressly required by the Bidding
Documents, and safety precautions and programs incident thereto.
F. CONTRACTOR does not consider that any further examinations,
investigations, explorations, tests, studies, or data are necessary for the performance
of the Work at the Contract Price, within the Contract Times, and in accordance with
the other terms and conditions of the Contract Documents.
G. CONTRACTOR is aware of the general nature of work to be performed by
OWNER and others at the Site that relates to the Work as indicated in the Contract
Documents.
21
H. CONTRACTOR has correlated the information known to CONTRACTOR,
information and observations obtained from visits to the Site, reports and drawings
identified in the Contract Documents, and all additional examinations, investigations,
explorations, tests, studies, and data with the Contract Documents.
I. CONTRACTOR has given ENGINEER written notice of all conflicts, errors,
ambiguities, or discrepancies that CONTRACTOR has discovered in the Contract
Documents, and the written resolution thereof by ENGINEER is acceptable to
CONTRACTOR.
J. The Contract Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for performance and furnishing of the
Work.
22
ARTICLE 9 -CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages 18 to 25 ,inclusive).
2. Performance Bond (pages 1 to 2 ,inclusive).
3. Payment Bond (pages 1 to 2 ,inclusive).
4. Other Bonds (pages to ,inclusive).
5. General Conditions (pages 00700-0 to 00700-40 ,inclusive).
6. Supplementary Conditions (pages 00800-41 to 00800-49 ,inclusive).
7. Specifications as listed in the table of contents of the Project Manual.
8. Drawings consisting of a cover sheet and sheets numbered 1-9,
inclusive, with each sheet bearing Columbia Heights, Minnesota.
9. Addenda (numbers 1 to 1 ,inclusive).
10. Exhibits to this Agreement (enumerated as follows):
a. CONTRACTOR'S Bid (pages 10 to 17 ,inclusive).
b. Documentatian submitted by CONTRACTOR prior to Notice
of Award (pages to ,inclusive).
c.
11. The fallowing which may be delivered or issued on or after the
Effective Date of the Agreement and are not attached hereto:
a. Notice to Proceed (pages 00640-1 to 00640-1 ,inclusive).
b. Work Change Directives.
c. Change Order(s).
B. The documents listed in Paragraph 9.O1.A are attached to this Agreement
(except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents may only be amended, modified, or supplemented as
provided in Paragraph 3.04 of the General Conditions.
ARTICLE 10 -MISCELLANEOUS
23
ARTICLE 10 -MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General
Conditions and the Supplementary Conditions.
10.02 Assignment of Contract
A. No assignment by a part;T hereto of any rights under or interests in the Contract
will be binding on another party hereto without the written consent of the party
sought to be bound; and, specifically but without limitation, moneys that may became
due and moneys that are due may not be assigned without such consent (except to the
extent that the effect of this restriction may be limited by law}, and unless specifically
stated to the contrary in any written consent to an assignment, no assignment will
release or discharge the assignor from any duty or responsibility under the Contract
Documents.
10.03 Successors and Assigns
A. OWNER and CONTRACTOR each binds itself, its partners, successors,
assigns, and legal representatives to the other party hereto, its partners, successors,
assigns, and legal representatives in respect to all covenants, agreements, and
obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or
unenforceable under any I,aw or Regulation. shall be deemed stricken, and all
remaining provisions shall continue to be valid and binding upon OWNER and
CONTRACTOR, who agree that the Contract Documents shall be reformed to
replace such stricken provision or part thereof with a valid. and enforceable provision
that comes as close as possible to expressing the intention of the stricken provision.
10.05 Other Provisions (if applicable).
24
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed this Agreement in
duplicate. One counterpart each has been delivered to OWNER and CONTRACTOR. All portions of
the Contract Documents have been signed or identified by OWNER and CONTRACTOR or on their
behalf.
This Agreement will be effective on ~ , t~ , 2010 (which is the Effective Date of the
Agreement).
nwrrFU
[CORPORATE SEAL)
(If OWI4TER is a corporation, attach evidence
of autharity to sign. If O WNER is a public
body, attach evidence of autharity to sign and
resolution or other documents authorizing
execution of O ER-CONTRACTOR
Agreement).
Designated Representative:
Name:_
Title:
Address:_
Phone:_
Facsimile:
[CORr~RATE SEAL]
Address for giving notices:
C~
l t t . `.:~`~ ~-J:--t 5`C~
License No.
(Where applicable}
Agent far service of process:
(If CONTRACTOR is a corporation or a
partnership, attach evidence of authority to
sign.)
Designated Representative:
Name: ~~ ~ - l 6 ~~
Title: ~ ~. ~'}
Address:
Phone: .~ a~"" c ~`~'
Facsimile: C~ ~ ' ~ - ~
25
CONTRACTOR:
PERFORMANCE BOND
Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
Ellingson Drainage, Inc.
56113 State Hwy 56
West Concord, MN 55985
OWNER (Name and Address}:
City of Columbia Heights
590 40th Ave.
Columbia Heights, MN 55421
CONTRACT
Effective Date of Agreement:
Amount: $398,616.50
Description (Name arzd Location):
BOND
Bond Number: 2109340
SURETY (Nance, and Address of Principal Place of Business):
North American Specialty Insurance Company
650 Elm Street
Manchester, NH 03101
June 7, 2010
Three Hundred Ninety Eight Thousand Six Hundred Sixteen Dollars and 50/100
2010 Trunk Sanitary Sewer Pipe Bursting, City Project No. 0813
Date (Not earlier than Effective Date of
Agreement): June 7, 2010
Amount: $398,616.50 Three Hundred Ninety Eight Thousand Six Hundred Sixteen Dollars and 50/100
Modifications to this Bond Form:
Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause
this Performance Bond to be duly executed by an authorized officer, agent, or representative.
CONTRACTOR AS PRINCIPAL
SURETY
Ellingson Drainage, Inc... (Seal) North American Specialty Insurance Company (Seal)
Contractor's Nan~~ and rpo e Seal Surety's Name~and Corporate `Seat
By: ~ ` _ ~~ By:
S' ° ur
~~ . r
~_,~--~
Print Name
- ~~,
Signature (A-tiaeh Power of Attorney)
f
Brian J. Oestreich
Print Name
Attornev-in-Fact
Title
. ~ ~ , ,~ r~
Signature ~.
Sandra M. Doze Surety Account Rep
Title
Note: Provide execution by additional parties, such as joint venta~r•ers, if necessary.
EJCDC C-610 Performance Bond
Prepared by the Engineers Joint Contract Documents Committee.
Page 1 of 1
Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators,
successors, and assigns to Owner for the performance of the Contract, which is incorporated herein by
reference.
1. If Contractor performs the Contract, Surety and Contractor have no obligation under this Bond, except to
participate in conferences as provided in Paragraph 2.1.
2. If there is no Owner Default, Surety's obligation under this Bond shall arise after:
2.1 Owner has notified Contractor and Surety, at the addresses described in Paragraph 9 below, that
Owner is considering declaring a Contractor Default and has requested and attempted to arrange a
conference with Contractor and Surety to be held not later than 1S days after receipt of such notice
to discuss methods of performing the Contract. If Owner, Contractor, and Surety agree, Contractor
shall be allowed a reasonable time to perform the Contract, but such an agreement shall not waive
Owner's right, if any, subsequently to declare a Contractor Default; and
2.2 Owner has declared a Contractor Default and formally terminated Contractor's right to complete
the Contract. Such Contractor Default shall not be declared earlier than 20 days after Contractor
and Surety have received notice as provided in Paragraph 2.1; and
2.3 Owner has agreed to pay the Balance of the Contract Price to:
1. Surety In accordance with the terms of the Contract; or
2. Another contractor selected pursuant to Paragraph 3.3 to perform the Contract.
3. When Owner has satisfied the conditions of Paragraph 2, Surety shall promptly, and at Surety's expense,
take one of the following actions:
3.1 Arrange for Contractor, with consent of Owner, to perform and complete the Contract; or
3.2 Undertake to perform and complete the Contract itself, through its agents or through independent
contractors; or
3.3 Obtain bids or negotiated proposals from qualified contractors acceptable to Owner for a contract
for performance and completion of the Contract, arrange for a contract to be prepared for execution
by O`vner and contractor selected with Owner's concurrence, to be secured with performance and
payment bonds executed by a qualified surety equivalent to the bonds issued on the Contract, and
pay to Owner the amount of damages as described in Paragraph 5 in excess of the Balance of the
Contract Price incurred by Owner resulting from Contractor Default; or
3.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor, and
with reasonable promptness under the circumstances:
1. After investigation, determine the amount for which it may be liable to Owner and, as soon as
practicable after the amount is deternined, tender payment therefor to Owner; or
2. Deny liability in whole or in part and notify Owner citing reasons therefor.
4. If Surety does not proceed. as provided in Paragraph 3 with reasonable pramptness, Surety shall be
deemed to be in default on this Bond 15 days after receipt of an additional written notice from Owner to
Surety demanding that Surety perform its obligations under this Bond, and Owner shall be entitled to enforce
any remedy available to Owner. If Surety proceeds as provided in Paragraph 3.4, and Owner refuses the
payment tendered or Surety has denied liability, in whole or in part, without further notice Owner shall be
entitled to enforce any remedy available to Owner.
5. A$er Owner has terminated Contractor's right to complete the Contract, and if Surety elects to act under
Paragraph 3.1, 3.2, or 3.3 above, then the responsibilities of Surety to Owner shall not be greater than those
of Contractor under the Contract, and the responsibilities of Owner to Surety shall not be greater than those
of Owner under the Contract. To the Iimit of the amount of this Bond, but subject to commitment by Owner
of the Balance of the Contract Price to mitigation of costs and damages on the Contract, Surety is obligated
without duplication for:
EJCDC C-610 Performance Bond
Prepared by the Engineers Joint Contract Documents Committee.
Page 2 of 2
5.1 The responsibilities of Contractor for correction of defective Work and completion of the Contract;
5.2 Additional legal, design professional, and delay costs resulting from Contractor's Default, and
resulting from the actions of or failure to act of Surety tinder Paragraph 3; and
5.3 Liquidated damages, or if no liquidated damages are specified in the Contract, actual damages
caused by delayed performance ornon-performance of Contractor.
6. Surety shall not be liable to Owner or others for obligations of Contractor that are unrelated to the
Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such
unrelated obligations. No right of action shall accrue on this Bond to any person. or entity other than Owner
or its heirs, executors, adaninistrators, or successors.
7. Surety hereby waives notice of any change, including changes of time, to Contract or to related
subcontracts, purchase orders, and other obligations.
8. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent
jurisdiction in the location in which the Work or part of the Work is located, and shall be instituted within
two years after Contractor Default or within two years after Contractor ceased working or within two years
after Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the
provisions of this paragraph are void or prohibited by law, the minimum period of limitation available to
sureties as a defense in the jurisdiction of the suit shall be applicable.
9. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the address shown on the signature
page.
10. When this Bond has been furnished to comply with a statutory requirement in the Location where the
Contract was to be performed, any provision in this Bond conflicting with said statutory requirement shall be
deemed deleted herefrom and. provisions conforming to such statutory requirement shall be deemed
incorporated herein. The intent is that this Bond shall be construed as a statutory bond and not as a common
law bond.
11. Definitions.
11.1 Balance of the Contract Price: The total amount payable by Owner to Contractor under the
Contract after all proper adjustments have been made, including allowance to Contractor of any
amounts received or to be received by Owner in settlement of insurance or other Claims for
damages to which Contractor is entitled, reduced by all valid and proper payments made to or on
behalf of Contractor under the Contract.
112 Contract: The agreement between Owner and Contractor identified on the signature page,
including all Contract Documents and changes thereto.
11.3 Contractor Default: Failure of Contractor, which has neither been remedied nor waived, to perform
or otherwise to comply with the terms of the Contract.
1.1.4 Owner Default: Failure of Owner, which has neither been remedied nor waived, to pay Contractor
as required by the Contract or to perform and complete or otherwise comply with the other terms
thereof.
FOR INFORMATION ONLY - (Nntne, Address and Telephone)Cobb Strecker Dunphy & Zimmermann, Inc.
Surety Agency or Broker: 150 South Fifth Street, Suite 2800, Minneapolis, MN 55402 612-349-2400
Owner's Representative (Engineer or outer party}: City of Columbia Heights Engineering Dept., Columbia Heights, MN
EJCDC C-610 Performance Bond
Prepared by the Engineers Joint Contract Documents Committee.
Page 3 of 3
PAYMENT BOND
Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
Ellingson Drainage, Inc.
56113 State Hwy 56
West Concord, MN 55985
OWNER (NaiTZe aiad Address):
City of Columbia Heights
590 40th Ave.
Columbia Heights, MN 55421
CONTRACT
SURETY (Name, aj~zd ~1ddi•ess of Principal Place of
Birsirtess):
North American Specialty Insurance Company
650 Elm Street
Manchester, NH 03101
Effective Date of Agreement: June 7; 2010
Amount: $398,616.50 Three Hundred Ninety Eight Thousand Six Hundred Sixteen Dollars and 50/100
Description (Name afad Location):2010 Trunk Sanitary Sewer Pipe Bursting, City Project No. 0813
BOND
Bond Number: 2109340
Date (Not earlier than Effective Date of
Agreement): June 7, 2010
Amount: $398,616.50 Three Hundred Ninety Eight Thousand Six Hundred Sixteen Dollars and 50/100
Modifications to this Bond Form:
Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each
cause this Payment Bond to be duly executed by an authorized officer, agent, or representative.
CONTRACTOR AS PRINCIPAL
SURETY
Note; Provide execution by additional parties, s~.~ch crs joiy~~t vertti~rref~s, f f~ecesscrry.
{iV1~~'00150a;1} EJCDC G615(A) Payment Bond n~Iarch 2008
Prepared by the lingineers Joint Contract Documents Committee.
I'a~e I of 3
1. Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators,
successors, and assigns to Owner to pay for labor, materials, and equipment filritished by Claimants for use
in the performance of the Contract, which is incorporated herein by reference.
2. With respect to Owner, this obligation shall be null and void if Contractor:
2.1 Promptly makes payment, directly or indirectly, for all sums due Claimants, and
2.2 Defends, indemnifies, and holds harmless Owner from all claims, demands, liens, or suits alleging
non-payment by Contractor by any person or entity who furnished labor, materials, or equipment
for use in the performance of the Contract, provided Owner has promptly notified Contractor and
Surety (at the addresses described in Paragraph 12) of any claims, demands, liens, or suits and
tendered defense of such claims, demands, liens, or suits to Contractor and Surety, and provided
there is no Owner Default.
3. With respect to Claimants, this obligation shall be null and void if Contractor promptly makes payment,
directly or indirectly, for all sums due.
4. Surety shall have no obligation to Claimants under this Bond until:
4.1 Claimants who are employed by or have a direct contract with Contractor have given notice to
Surety (at the address described in Paragraph 12) and sent a copy, or notice thereof, to Owner,
stating that a claim is being made under this Bond and, with substantial accuracy, the amount of the
claim.
4.2 Claimants who do not have a direct contract with Contractor:
1. Have furnished written notice to Contractor and sent a copy, or notice thereof, to Owner, within
90 days after having last performed labor or last furnished materials or equipment inchided in the
claim stating, with substantial accuracy, the amount of the claim and the name of the party to
whom the materials or equipment were furnished or supplied, or for whom the Labor was done or
perforned; and
2. Have either received a rejection in whole or in part from Contractor, or not received within 30
days of furnishing the above notice any communication from Contractor by which Contractor had
'indicated the claim :dill be paid directly or indirectly; and
3. Not having been paid within the above 30 days, have sent a writtela notice to Surety (at the
address described in Paragraph 12) and sent a copy, or notice thereof, to Owner, stating that a
claim is being made under this Bond and enclosing a copy of the previous written notice
furnished to Contractor.
5. If a notice by a Claimant required by Paragraph 4 is provided by Owner to Contractor or to Surety, that is
sufficient compliance.
6. Reserved.
7. Surety's total obligation shall not exceed the amount of this Bond, and the amount of this Boyd shall be
credited for any payments made in good faith by Surety.
8. Amounts owed by Owner to Contractor tinder the Contract shall be used for the performance of the
Contract and to satisfy claims, if any, under any performance bond. By Contractor furnishing and Owner
accepting this Bond, they agree that all funds earned by Contractor in the performance of the Contract are
dedicated to satisfy obligations of Contractor and Surety under this Bond, subject to Owner's priority to use
the fiords for the completion of the Work.
9. Surety shall not be liable to Owner, Claimants, or others for obligations of Contractor that are unrelated
to the Contract. Owner shall not be liable for payment of any costs or expenses of any Claimant under this
Bond, and shall have tinder this Bond no obligations to make payments to, give notices on behalf of, or
otherwise have obligations to Claimants under this Bond.
{n1w001504;1} E.ICDC C-615(A) Payment Bond Alarch 2008
Prepared by the Engineers Joint Contract Documents Cammittec.
Page 2 of 3
10. Surety hereby waives notice of any change, inchlding changes of time, to the Contract or to related
subcontracts, purchase orders, and other obligations.
11. No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent
jurisdiction in the location in which the Work or part of the Work is located or a$er the expiration of one
year from the date (1) on which the Claimant gave the notice required by Paragraph 4.1 or Paragraph 4.2.3,
or (2) on which the last labor or service was performed by anyone or the last materials or equipment were
furnished by anyone under the Contract, whichever of (1) or (2) first occurs. If the provisions of this
paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense
in the jurisdiction of the suit shall be applicable.
12. Notice to Surety, Owner, or Contractor shall be mailed or delivered to tl7e addresses shovm an the
signature page. Actual receipt of notice by Surety, Owner, or Contractor, however accomplished, shall be
sufficient compliance as of the date received at the address shown on the signature page.
13. When this Bond has been furnished to comply with a statutory requirement in the Location where the
Contract was to be performed, any provision in this Bond conflicting with said statutory requirement shall be
deemed deleted herefrom and provisions conforming to such statutory requirement shall be deemed
incorporated herein. The intent is that this Bond shall be construed as a statutory Bond and not as a common
law bond.
14. Upon request of any person or entity appearing to be a potential beneficiary of this Bond, Contractor
shall promptly fiirlish a copy of this Bond or shall permit a copy to be made.
15. Definitions
15.1 Claimant: An individual or entity having a direct contract with Contractor, or with afirst-tier
subcontractor of Contractor, to famish labor, materials, or equipment for use in the performance of
the Contract. The intent of this Bond shall be to include without Iimitation in the terms "labor,
materials or equipment" that part of water, gas, power, light, heat, oil, gasoline, telephone service,
or rental equipment used in the Contract, architectural and engineering services required for
performance of the Work of Contractor and Contractor's subcontractors, and all other items for
which a mechanic's lien may be asserted in the jurisdiction where the labor, materials, or
equipment were filrnished.
15.2 Contract: The agreement between Owner and Contractor identified on the signature page,
including all Contract Documents and changes thereto.
15.3 Owner Default: Failure of Owner, which has neither been remedied. nor waived, to pay Contractor
as required by the Contract, or to perform al?d camplete or otherwise comply with the other terms
thereof.
FOR INFORMATION ONLY- (Name, Adds°ess, and Telephor~e)Cobb Strecker Dunphy & Zimmermann, Inc.
Surety Agency or Broker: 150 South Fifth Street, Suite 2800, Minneapolis, MN 55402 612-349-2400
Owner's Representative (Engineer or° other°): City of Columbia Heights Engineering Dept., Columbia Heights, MN
{b1w001504;1} E.1CDC C-615(A) Payment Bond March 2008
Prepared by the Engineers Joint Contract Documents Committee.
Pa~c 3 of 3
ACKNOWLEDGMENT OF CORPORATION
State of Minnesota
~`" ss.
County of ~-' _
On this p~-~1 day of- w , ?010 before me appeared
to me personally known, wha, being by me duly sworn, did say that (s} he is/are the
instrwnent is the corporate seal of said corporation, / -~~~`~„~s~
so state, and strike out above as to corporate seal) and that said instrument was
Directors; and that said
said corporation.
- ..~
~:~ .
of
a corporation, that the seal affixed to the forgoing
' r G''~--° ([1~ no seal,
~cuted in beh f of said corporation by authority of its Board of
acknowledged said instrument to be the free act and deed of
~~ f ~ ~,.
Nota ~ P lice ,= ~ ounty, ; '~~I ~ ~-
My commission expires , ~ _~ ~'r~ :- _.~~
~/ -t _
ACKNOWLFDGMENT OF COI2POI2ATE SURETY
State of Minnesota
ss.
Cowlty of Hennepin
On this 7th day of June , 24 l0 ,before me appeared Brian J. Oestreich
to the personally known, wha being by me duly sworn, did say that (s)he is the Attorney-in-Fact of North American Specialty
Insurance Company , a corporation, that the seal affxed to the foregoing instrument
is Che corporate seal of said corporation and that said instrument was executed in behalf of said corporation by authority of its Board of
Directors; and that said Brian J. Oestreich acknowledged said instrument to be
the free act and deed of said corporation.
~ SAN~t~A lE
'': NOTARY pU~.iC> St}TA
My dafi.3l,20tt
Y ~ ~
6_. (''
Notary Public County, ...
My commission expires
NAS SURETY GROUP
NORTH AMERICAN SPECIALTY INSURANCE COMPANY
WASH~IGTON INTERNATIONAL INSURANCE COMPANY
GENERAL POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS, THAT North American Specialty Insurance Company, a corporation duty organized and existing under
laws of the State of New Hampshire, and having its principal office in the City of Manchester, New Hampshire, and Washington International
Insurance Company, a corporation organized and existing under the laws of the State of Arizona and having its principal office in the City of Itasca,
Illinois, each does hereby make, constitute and appoint:
BRUCE N. TELANDER, JOHN P. MARTINSEN, R W. FRANK, DONALD R OLSON, JOHN E. TAUER,
CRAIG REMICK, R SCOTT EGGINTON, JOSHUA R LOFTIS, BRIAN J. OESTREICH and SANDRA M. DOZE
JOINTLY OR SEVERALLY
Its trne and lawful Attorney(s)-in-Fact, to make, execute, seal and deliver, for and on its behalf and as its act and deed, bonds or other writings
obligatory in the nature of a bond on behalf of each of said Companies, as surety, on contracts of suretyship as are or may be required or permitted by
law, regulation, contract or otherwise, provided that no bond or undertaking or contract or suretyship executed under this authority shall exceed the
amount of:
TWENTY-FIVE MILLION ($25,000,000.00) DOLLARS
This Power of Attorney is granted and is signed by facsimile under and by the authority of the following Resolutions adopted by the Boazds of
Directors of both North American Specialty Insurance Company and Washington International Insurance Company at meetings duly called and held
on the 24a' of March, 2000:
"RESOLVED, that any two of the President, any Executive Vice President, any Vice President, any Assistant Vice President, the Secretary or any
Assistant Secretary be, and each nr any of them hereby is authorized to execute a Power of Attorney qualifying the attorney named in the given Power
of Attorney to execute on behalf of the Company bonds, undertakings and all contracts of surety, and that each or any of them hereby is authorized to
attest to the execution of any such Power of Attorney and to attach therein the seal of the Company; and it is
FURTHER RESOLVED, that the signature of such officers and the sea! of the Company may be affixed to any such Power of Attorney or to any
certifreate relating thereto by facsimile, and any such Power of Attorney ar certificate bearing such facsimile signatures or facsimile seal shall be
bindang upon the Company when so affixed and in the future with regard to any bond, undertaking or contract of surety to which it is attached:"
~uutuuutn
\O~e ~GV~,t,7Y!'kP41j4,,. !/~~ .t~'~°~a"ftBMAj~"°~.
r cP~`PQR,rF~~= By ~~'t ' C~ ,~~` `~''`',
~~. SEAi_ :n. r CORPORATE ~=
s ~ ~ a Stevw P. Aadersoq Preaideat & Chtef Execvtlve Omcc oC Wuhiagtoa Internadona! [nannn« Company & ~ ffi ~ EA ~ ~
~,~~ iQ~3 Q~: t) y Vke Preaidmt of North American specLity fnauraece Company s~
David hL Gyman, Yia Prcaddmt of Wei6ln'tea Internatianai tnmcan« Company &
Vke Peerideot of North American Speciahy lvaaenn« Compaay
IN WITNESS WHEREOF, North American Specialty Insurance Company and Washington International Insurance Company have caused their
official seals to be hereunto affixed, and these presents to be signed by their authorized officers this 5th day of June 20 Q8 .
North American Specialty Insurance Company
Washington International Insurance Company
State of Illinois
County of Du Page ss:
On this sth day of Jane , 20~ before me, a Notary Public personally appeared Steven P. Anderson ,President and CEO of
Washington International Insurance Company and Vice President ofNorth American Specialty Insurance Company and David M. Layman ,
Vice President of Washington International Insurance Company and Vice President of North American Specialty Insurance Company,
personally known to me, who being by me duly sworn, acknowledged that they signed the above Power of Attorney as officers of and
acknowledged said instrument to be the voluntary act and deed of their respective companies-
"(}FFf(~Ai. SPAL"
NNAD. SBIENS
~7 ~S ~ of Ilfmoia
f~mi~n Etta 1fY0Fi/2D11
1~6NvriA ~ ~.~~
Donna D. Sklens, Notary Public
I, James A. Carpenter the duly elected Assistant Secretary of North American Specialty Insurance Company and Washington
International Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney given by said North
American Specialty Insurance Company and Washington International Insurance Company, which is still in full force and effect
IN WITNESS WI~REOF, I have set my hand and affixed the seals of the Companies this 7TH day of JUNE 20 I O
~--~,G'
James A Cary«ter, Via Praideat & Assstant Seuetary of Washington International insurance Company &
North Amman Speaalty LuLran« Compaay
TIF'1 ~. ~~„ ~ +~ OP ID BE DATE(MMID4/YYYYj
ELLINGS 06/02/10
PRODUCER THEE CERTIFICATE IS ISSUED AS A MATTER OF INFORMATEON
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFlCA7E
The MacKenzie Agency HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
P . O . Box 12 0 ALTER THE COVERAGE AFFORDED t3Y THE POLICIES BELOW-
St. Peter ri~7 55x82
Phones 507-931-4482 !, ENSURERS AFFORDING COVERAGE ' NAEG #
INSURED -.. _.-_ -_.__.__'..
INSURcR;~.. Contanental Western Group
- ~_
fNSUfiER B '
---
Ellingsan Drainagge Inc INSURERc
56113 State HWY 56 PO Box 68 - - - --- --
--
West Concord MN 55985 INSURER D
----- -
INSURER ~:
COVERAGES
_ _
- - ~ - - ~D TO TriE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITNSTANUING
ANY REQUIREMEhJi, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO VIHICH THI5 CERTIFICATE MAY BE ISSUED OR
6J,AY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIF_S DESCRIBED HEREIN I5 SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
PgLICIES. AGGREGATE LIMITS S}tOrh'N MAY HAVE SEEN REDUCED BY FA(D CLAIMS.
TNSR-y~Al3D'L _..__. _ -.___.._ ._. _ ___
LTR ~ NSRD TYPE OF INSURANCE POLICY NUMBER P011CV E ~ P LI Y EXPiRATtON~ ~ -~
DATE MMIDDIYYYY) DATE (MM/DDlYYYY) LIMtTS
GENERAL LIABILITY EACH OCCURRENCE S 1 r 666 ~ {} (} (j
A I ~{ COMMERCIAL GENERAL LIABILITY
____ CWP2612506- 25 64/01/10 04~01~11 PREMISES (Ea occurerrce}
_.._.-.---...... S 100 d~Q
_ s
I I ..LAIMS rAADE ~ OCCUR
~ ~ MED EXP (Any one person) S 5 , 0 0 0
}' OC'P LIABILITY PERSONAL&RDV INJURY $ 1, 066, 17OQ
X XCU IL~TCLUDED
-
~ ~ ~
GENT=,=2AL AGGREGATE 2
008
000
} -- --
~ ! (
-__- .
,
,
.. ~- -- _-~
G~fv L AGGftcGATE LIMIT APPLIES PER:
-- I PRODUCTS - COMPlOP AGG E 3 2 , 0O 6 r !} O6
X POLICY ~ PRO-
LOC
JECT ~ _..~--------- '-- _
~ _
RUTOMOBtLE LIABILITY ~ I
~ ~ ~ ~'~
I At:~Y AUTO
I
' COMBINED 51NGt.E LIM1AIT
(Ea accident}
$ ~.. p ~ ~} b r a ~ b
t--- -- -_ _ _ -- --
-
.2C
AL.t- ~:3LVNED AUTOS I -
----
I BODILY INJURY
'
$
r SCHEDULED AUTOS I
(Per person)
1
f
, X
- IIIRE.D A.UT~OS ~
~ CWP2612506- 25
04lOII10
04(01/11 - ----. -._-.----'--
!BODILY I
U -----..__
X ~
--
NON-CV~tNED AUTOS '
~
i NJ
RY
CPer accident]
-._..~~
~ $
C
_~--- - ~ - I
~ I
I
PROPERTY DAMAGE __ __...
I --
c
(Per accidenq
RAGE LIABILITY f AUTO ONLY - EA RCCIDENT $
+ ANY AUTO
~ EA ACC
OTHER THAN _ T~
!
I
~ _--
-.. -_._~ f
_._.-._ ~ i AUTO ONLY: ,
.1GG I __.
S
1 i
FXCESSlUhRSRELLALtABti €TY i
I
i
EACHOi;CURRENOE
$ ~t (j00r Qa[)
A ~ I.
~ ~ OGCJR ~ CLAitu4SMADE
_
(°Cjf,~6~.2a~'3'~ --25 I
Q~/(}1/~Q ~
Q4fQ,1,f1I,
AGGREGATE _ --
S ~B~(J(}i (jQQ
'
i ~ ' i S
r
~ OEDUC ITBL E _
} -.
I ~
- --'-- $
~ REi61J t lOtd $ 10
(} ~} Q ~-- -
. r
I +NORhERS COYrPEN~ATION
AND EMPLOYERS LIABILITY Y
' N ~ I
~ ~
I ~ TORY LIMITS i UER
~
~
,
,~ AfJYPROPRtFTOnPAnTPv R/EXECtiLI`J'~ ~
i
i
i
C1i-Ff4ER (tGrMBtr2 EXCLUDLC3~ ~ ~
~{/;7~'26i2536_2
5
~ ~ ~ ~
_
(jd ,~,. Icy ~ (pq,101/11 ._...
..
__ _
S ~. Ir}Q6
{}(j(}
E.L ACHACCtDENt~
F r
f
f
f
~
,Mandatory ~n NH} ~
I -
---
_
-
"
Is yes des rioe ~.md=r
! -
E ~ pISEASE
- EA EMPLOYEE 5 ~. , O (~ ~ a (} ~ [}
_ _-._~___ __- ~,-- -----
-~ SPECIAL PROVISION5 be gin: E. LESEASE POLICY L'f~71T I $ 1 r 000 a 6 06
OTHER k I ---
~EI~'Z'E17fLCASE EQL32?' I C~IP2612506-25 C74J61/10 I 04/OIJ11 ! LINdIT 500,63Q0
r
i I
~I ~~~~~~~~~ 50 0
_...
w e
r;r5r'ft3PT(ON OF OPER~",T30^!S I LCN`a.TIONS,' VEHICLES 1 EXGLt;..~4~~, Ai;i>EL`~ t?Y cNUO,iSEt/EN'S 1 SFi t;t~".L PRV
JtSftJNS `-- '--_------- -
--
~
^
ye. p~-~^ y±y'
('} ~^ yx
rV31~~~~.1..yv~=4 L1..6Y..:.RS$s.~dTT .° ~ CPL ~ i~t).~.~J,~3"1.-~41~ ~.A .w`~= ~-~}Z-~~i,,.lf~,~
~TII.ITa $2, 600, 000 I
~.~....me.._. ._-__..__._.__._._._-_._..--..-.. _...
CEE2T9F6GATE H43LDEF: GANCELLA'F@ON T^=.
ALlDITIOI~TAL INSt7R.EDm
CITY CIF` COLUMBIA HEIGHTS
637 38TH AVE CIE
COLUMBIA HEIGHTS MN' 55421.
SHOULD AFdY OF THE ABOVE DESC RISED POLICRES SE CANCELLED BEFORE THE EXPIRAFIdhi
DATE THERE-OF, TERE ISSUING ENSURER W:LC ENDEAVOR TO r.4AtL IQ DF.YS WRftTEN
`:OTiCE TC T tic GERTIF,CAt E HOLDER ^tAP~ED 70 f HE LEFT. ce1T FAELUFiE TC7 TKi SG' SHALL
tfv9POSE NO 08L1GAT14td 4R LIABILITY OF ANY KIND UPON 'i't@E ENSURER, fTS AGENTS OR
REPRESENTRTIVES.
~a.vacv ~;, (tvuyru ~~ OO 1988-2069 ACORD CORPORATION. All rights reserved.
The ACORD name and logo are registered marks of AGORD
23
CHANGE ORDER NO. 1
Project: Sanitary Sewer Pipe Bursting City Project: 0813
Central Avenue, 47 Avenue to 51 Court
Owner: City of Columbia Heights
637 38 Avenue N.E. Date of Issuance: November 15, 2010
Columbia Heights, MN 55421
Contractor: Ellingson Companies
PO Box 68 Engineer: City Engineer
West Concord, MN 55985
You are directed to make the following changes in the Contract Documents:
Description: Change in original contract price to compensate for work added to the contract by the City:
Water main conflicted with sanitary sewer main near manhole. Relocated water main and
installed at 7' depth instead of 10' to make repairs easier in the future.
Install new steps in reconstructed manhole.
Install seed and erosion control blanket at businesses.
Restore parking lots, Install new parking blocks, and Stripe lots.
Purpose of Change Order: The contract has been modified to add the changes.
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original Contract Time:
$ 398,616.50
Previous Change Orders No. — to No. _ Net Change from Previous Change Order:
None
Contract Price Prior to this Change Order: Contract Time Prior to this Change Order:
$ 398,616.50
Net Increase (Decrease) of this Change Order: Net Increase (Decrease) of Change Order:
$ 49,103.00
Contract Price with all Approved Change Orders: Contract Time with Approved Change Orders:
$ 447,719.50
Recommended Approved
B By:
City E A ineer Ellingson Companies
Approved r ; Approved 3 Date of Council Action
i ' ,..'-- ar 7 ' ---\ 0 :7_Z" ,,e,,t /--"--' I ;1) i 1 ?) I D
'Oary -' - erson, ayor Walter Fehst, City Manager
Attachment to Change Order No. 1
City Project 0813
Page 1 of 1
Owner: City of Columbia Heights
Contractor: Ellingson Companies
Project: Central Avenue Sanitary Sewer Pipe Bursting
Description of Changes:
The Public Works Department requested the following items.
Item No. Item Description Unit Quantity Unit Price Total Price
1 Relocate water main L.S. 1 $14,915.00 $14,915.00
2 Drill and install manhole steps L.S. 1 $ 669.00 $ 669.00
3 Seed and erosion blanket S.Y. 697 $ 3.30 $ 2,300.00
4 Furnish and install parking stops Each 8 $ 65.50 $ 524.00
5 Stripe parking lots L.S. 1 $ 440.00 $ 440.00
6 Remove bituminous parking lot S.Y. 866 $ 3.50 $ 3,031.00
7 Aggregate base class 5 or 7, CV C.Y. 120 $ 32.60 $ 3,912.00
8 Bituminous pavement Ton 188 $ 124.00 $23,312.00
TOTAL OF CHANGE ORDER NO. 1 $49,103.00
2 a 2
CHANGE ORDER NO. 1
Project: Sanitary Sewer Pipe Bursting City Project: 0813
Central Avenue, 47 Avenue to 51 Court
Owner: City of Columbia Heights
637 38 Avenue N.E. Date of Issuance: November 15, 2010
Columbia Heights, MN 55421
Contractor: Ellingson Companies
PO Box 68 Engineer: City Engineer
West Concord, MN 55985
You are directed to make the following changes in the Contract Documents:
Description: Change in original contract price to compensate for work added to the contract by the City:
Water main conflicted with sanitary sewer main near manhole. Relocated water main and
installed at 7' depth instead of 10' to make repairs easier in the future.
Install new steps in reconstructed manhole.
Install seed and erosion control blanket at businesses.
Restore parking lots, Install new parking blocks, and Stripe lots.
Purpose of Change Order: The contract has been modified to add the changes.
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original Contract Time:
$ 398,616.50
Previous Change Orders No. _ to No. _ Net Change from Previous Change Order:
None
Contract Price Prior to this Change Order: Contract Time Prior to this Change Order:
$ 398,616.50
Net Increase (Decrease) of this Change Order: Net Increase (Decrease) of Change Order:
$ 49,103.00
Contract Price with all Approved Change Orders: Contract Time with Approved Change Orders:
$ 447,719.50
Recommended Approved
By: By:
City E xineer Ellingson Companies
Approved ra,, . Approved ,y •/ , Date of Council Action
A dfl , Arita/ Igit'31 to
'� rson, ayor Walter Fehst, city Manager
Attachment to Change Order No. 1
City Project 0813
Page 1 of 1
Owner: City of Columbia Heights
Contractor: Ellingson Companies
Project: Central Avenue Sanitary Sewer Pipe Bursting
Description of Changes:
The Public Works Department requested the following items.
Item No. Item Description Unit Quantity Unit Price Total Price
1 Relocate water main L.S. 1 $14,915.00 $14,915.00
2 Drill and install manhole steps L.S. 1 $ 669.00 $ 669.00
3 Seed and erosion blanket S.Y. 697 $ 3.30 $ 2,300.00
4 Furnish and install parking stops Each 8 $ 65.50 $ 524.00
5 Stripe parking lots L.S. 1 $ 440.00 $ 440.00
6 Remove bituminous parking lot S.Y. 866 $ 3.50 $ 3,031.00
7 Aggregate base class 5 or 7, CV C.Y. 120 $ 32.60 $ 3,912.00
8 Bituminous pavement Ton 188 $ 124.00 $23,312.00
TOTAL OF CHANGE ORDER NO. 1 $49,103.00
Z3 a
CHANGE ORDER NO. 1
Project: Sanitary Sewer Pipe Bursting City Project: 0813
Central Avenue, 47 Avenue to 51 Court
Owner: City of Columbia Heights
637 38 Avenue N.E. Date of Issuance: November 15, 2010
Columbia Heights, MN 55421
Contractor: Ellingson Companies
PO Box 68 Engineer: City Engineer
West Concord, MN 55985
You are directed to make the following changes in the Contract Documents:
Description: Change in original contract price to compensate for work added to the contract by the City:
Water main conflicted with sanitary sewer main near manhole. Relocated water main and
installed at 7' depth instead of 10' to make repairs easier in the future.
Install new steps in reconstructed manhole.
Install seed and erosion control blanket at businesses.
Restore parking lots, Install new parking blocks, and Stripe lots.
Purpose of Change Order: The contract has been modified to add the changes.
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price: Original Contract Time:
$ 398,616.50
Previous Change Orders No. _ to No. Net Change from Previous Change Order:
None
Contract Price Prior to this Change Order: Contract Time Prior to this Change Order:
$ 398,616.50
Net Increase (Decrease) of this Change Order: Net Increase (Decrease) of Change Order:
$ 49,103.00
Contract Price with all Approved Change Orders: Contract Time with Approved Change Orders:
$ 447,719.50
Recommended Approved
By: By:
City E ineer Ellingson Companies
Approved rd, Approved B Date of Council Action
mss" ._.._,_ - GiiG �L �'�
_ Aar teary- 'rson, ayor Walter Fehst, City Manager
Attachment to Change Order No. 1
City Project 0813
Page 1 of 1
Owner: City of Columbia Heights
Contractor: Ellingson Companies
Project: Central Avenue Sanitary Sewer Pipe Bursting
Description of Changes:
The Public Works Department requested the following items.
Item No. Item Description Unit Quantity Unit Price Total Price
1 Relocate water main L.S. 1 $14,915.00 $14,915.00
2 Drill and install manhole steps L.S. 1 $ 669.00 $ 669.00
3 Seed and erosion blanket S.Y. 697 $ 3.30 $ 2,300.00
4 Furnish and install parking stops Each 8 $ 65.50 $ 524.00
5 Stripe parking lots L.S. 1 $ 440.00 $ 440.00
6 Remove bituminous parking lot S.Y. 866 $ 3.50 $ 3,031.00
7 Aggregate base class 5 or 7, CV C.Y. 120 $ 32.60 $ 3,912.00
8 Bituminous pavement Ton 188 $ 124.00 $23,312.00
TOTAL OF CHANGE ORDER NO. 1 $49,103.00