HomeMy WebLinkAboutJuly 10, 1981COLUMBIA HEIGHTS PARK BOARD
SPECIAL MEETING
JULY lO, 198l
This meeting'was called in order that a recommendation on the Sullivan
Lake Development bid opening of July 8th, t981 could be presented to
the City Council at their meeting on July 13, ]981.
ROLL CALL:
Members Present: .William Hollom, doAnn Melin, John Murzyn, Jim Fowler,
John Starcevic, Thomas Rejzer.
Members Absent: Walter Logacz
Also Present: Fredrick Salsbury, Public Works Director; George Brown,
City Engineer.
SULLIVAN LAKE DEVELOPMENT
Salsbury explained in detail the specifics of the bids received on July 8th.
Five bids were presented with the low base bid being submitted by Minnesota
Valley Landscaping at the price of $482,168.t0. The bids received were all
higher than the Engineering estimate. (Refer to attachment)
Motion by Melin, seconded by Fowler that the following recommendation be
presented to the City Council:
RECOMMENDATION:
To accept the base bid of Minnesota Vat]ey Landscap-
ing as given--S482,168.10, with the difference
between the base bid and the budget being covered
by monies from the Sullivan Lake Fund.
ALTERNATE #]:
To a~ccept the base bid of Minnesota Valley Land-
scaping but including the following deducts: (a)
south shore pathway (b) storm headwatl (c)
concrete oiling. This would reduce the project
price to $402,997.20.
ALTERNATE #2:
To accept the base bid of Minnesota Valley Landscaping
but to include the deducts as noted in the Public
Works Recommendation. Project price--S408,789.45.
ALTERNATE #3:
If additions could be made to Alternate #1, or
Alternate #2, the following is a priority list of those
additions.
1. Complete arbor $20,430.00
2. Pathway--N.E. loop
13,237.25
3. Storm headwall 27,211.40
Tennis court lighting 7,000.00
COLUMBIA HEIGHTS PARK BOARD
SPECIAL MEETING
JULY 10, 1981
Page 2
All ayes, motion carried.
ADJOURNMENT
Motion by Fowler, seconded by Melin to adjourn. All ayes, motion carried.