TO: Robert S. Bocwinski, City Manager
FROM: M. Rebecca Loader, Library Director]'¥o~
SUBJECT: Operational Report #14 (January 1-Januarv 12, 1090)
DATE: January 12, lqqO
Significant accomplishments
A. The Board of Trustees met January 2.
B. The Friends of the Library met January 8. They set the dates for the
June booksale and the fall salad luncheon.
C. Fifty-five people attended the January lO senior citizen program.
D. The pay phone in the lobby was changed over to touch-tone on January 11
to accommodate calling cards and functions which require push buttons.
Departmental goals
A. Jeanine Schmidt started work January 2 as a full-time employee.
B. Klm Briley started work January 2 as a part-time choreperson.
C. The Friends worked on the re-labelling project January 9.
D. The final inspection on the mechanical work at the library has been
re-scheduled for January 19.
Issues and problems
A. The roof leaked January 8. Ail Systems Roofing was notified.
B. O~ January 11, a window was broken on the east side of the building.
C. On January 2, a muskrat was removed from the exterior stairwell.
Circulation LIBGIS
December 1088 1989 December lq88
Adult 6,1~8 4,360 Reference 1614
Juvenile A,175 3,277 Directional A 255
1~,373 7,637 Directional B 385
Working days 24
lqSq
1385
~62
54
23