HomeMy WebLinkAboutMar 1, 1961OFFICIAL~ PROCEEDINGS
Special'meeting
March 1, 1961
Meeting called to order at 8:05 p.m.
McCline, Orendorff - present.
Roll Call - Armstrong, King,
Chies - absent.
This special meeting is hel~ for the purpose of holding hearings on
special assessments for work previously constructed.
Hearing held on Project No.359, concrete paving of alley' east of UPland
crest and north of 47th Ave. After much discussion this assessment was
reduced by $1250.00, which was for dirt transferred to the Stinson Blvd.
street opening project.. .It was also agreed to assess this project on a
per lot basis rather than per front foot.
Motion by King seconded by Orsndorff, that project No.359 be assessed
at a total of $8350.00 on a per lot basis, including the City Property
considered three lots, making a total,of 11 assessed lots, at a cost
of $759.09 per lot based on 10 years for payment, and $1250.00 transferred
to the Stinson Blvd. Street opening. Roll Call - All Ayes.
Hearing held on Project No.393, Street opening - Tyler St.' 44th to 45th,
$1.60 per front foot with 2 years for payment.
Motion by McCline seconded by King, that assessment rolls ~r project
No.393 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.400, Street opening-- Lincoln St.,North of
37th Avenue, $3.~01 per'front foot with 3 years for payment. ~
Motion by McCline seconded by Orendorff, that assessment rolls for project
No.400 be adopted as presented. Roll Call - All Ayes.
Hearing held on P~uject No.401, Alley Asphalt Mat $1.66 per front'fo°t
with 3 years for payment. A question was raised by some citizens re-
garding th~ alley design and they were informed the contractor would be
called ba~ in to make any.neqessary, corrections ....
Motion by King seconded by Orendorff, that assessment rolls for project
No.401 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.407,~ curb & Gutter $2~46 per front foot for
Street and 82¢ per front' foOt for Avenue with 5.years for payment.
Motion by King seconded by McCline, that assessment rolls for Project
No.407 be adopted as preSented, deleting curb on 37th Avenue, 2nd Street
to alley, and driveways involved will be billed separately. Roll Call-All'Ayes.
Hearing held on Project No.411, Asphalt Mat $2.91 per front footfon street
and 97¢ per front foot for Avenue with 8 years for payment. Johnson Street
from 39th to approximately 39~, $2.50 per front foot for Street and 83¢ per
front foot for Avenue.
Motion by McCline seconded by Orendorff, that assessment rolls for Project
No.411 be adopted as presented. Roil Call- All Ayes.
Hearing held on Project No.413, Concrete alley paving $3.95 per front foot,
except alley Main-2nd St., 40th to 41st,$4.95 per front foot as storm drain
was installed, with 8 years for payment. The problems reported by
residents at 4053 Washington and 3802 Reservoir Blvd. will be checked into
by the City Engineer.
Motion by King seconded by ~cCline, that assessment rolls for Project
No.413 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No. 414, Street base work on Jefferson, 49th to
51st, $2.87 per front foot with 5 years for payment.
Motion by McCline seconded by Orendorff, that assessment rolls for
Project No.414 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.415, Sidewalk $2.15 per front foot with
5 years for payment.
Motion by King seconded by Orendorff, that assessment rolls for Project
No.415 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.425, Sanitary Sewer & Watermain 49th Avenue,
Central to Fairway Drive, $3.80 per front foot for sewer, $4.264 per fgont
foot for water, $4,613.01 Hilltop 3 and $2,126.43 (City Share), with 10
years for payment.
M~tion by McCline seconded by King, that assessment rolls for Project
No.425 be adopted as presented. Roll Call - A%l Ayes.
Project No.427 Sanitary sewer, 39th Avenue west from Arthur 250 feet
was withheld.
Hearing held on Project No.430, Sanitary Sewer and Watermain, Lincoln
Street 37th to 39th, $9.93 per front foot with 8 years for payment.
Motion by McCline seconded by King, that assessment rolls for Project
No.430 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.431, Watermain on 3rd Street, 38th to 40th,
$5.03 per front foot with 10 years for payment.
Motion by Orendorff seconded by King, that assessment rolls for Project
No.431 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No.432, Alley opening & Base between Central
and Tyler from 45th to 46th, 32¢ per front foot with one year for payment.
Motion by King seconded by McCline, that assessment rolls for Project.
No. 432 be adopted as presented. Roll Call - All Ayes.
Hearing held on Project No. 428, Curb & Gutter and Asphalt Mat and Base
in Sheffield Subdivision, $8.60 per front foot for Street and Avenue,
$2.86 per front foot for Avenue where no street improvement was made,
with 8 years for payment.
Motion by McCline seconded by King, that assessment rolls for Project
No.428 be adopted as presented. Roll Call - All Ayes.
Resolution offered by King seconded by Orendorff, Adopting assessment
rolls for the following Local improvements and determining that said improvem~
ments be made and ratifying and confirming all other proceedings, heretofore
had: Special assessment numbers 359, 393, 400,401,407,411,413,414,415,
~25, 428, 430, 431, 432. (As per attached Resolution) Roll Call-All Ayes.
First reading Ordinance No.514, Rezoning the Easterly 107.30 feet of
Lots 1,2,and 3, Block 2, Rearrangement of Block mA'. Columbia Heights
Annex to Minneapolis, to C-2-S Commercial.
First reading Ordinance No.515, Being an ordinance authorizing transfer
of title of LOt 5, Block 1, Rearrangement of Block "D', C.H. Annex to
Minneapolis, except the West 351 feet thereof.
Motion by McCline seconded by King, that the meeting adjourn at
12:30 p.m. Roll Call - All Ayes. ...~ /~-,../~~
~ecre~ar ' ~