RESOLUTION
AUTHORIZING AND ESTABLISHING LIHITATIONS ON
BLASTING AND ROCK CRUSHING IN CONJUNCTION WITH
THE BURLINGTON-NORTHERN RAILROAD CONSTRUCTION PROJECT
WEST OF CALIFORNIA STREET N,E, NORTH OF 37TH AVENUE,
BE l'F HERESY RESOLVED by the City Council of the City of
Columbia Heights, that
WHEREAS, theCity of Columbia Heights and Burlington-Northern, lnc.
entered into an agreement dated February 8, ]971 anticipating
exchanges of properties, relocation of certain utilities
and proposals regarding procedures on construction, and
WHEREAS, Burlington-Northern and their prime contractor,
Park Construction,Company are now prepared to proceed with
construction on The site consisting of earth moving, blasting
and rock crushing.
NOW, THEREFORE, SE IT RESOLVED that the city of Columbia
Heights authorizes the proposed construction work to
proceed with the following governing conditions:
No operations to proceed before 6:00 a.m. nor after
10:00 p.m. on the site.
Blastingto be done no more than once a day between
8:00 a.m. and 4:30 p.m.
That all structures on Hain Street and California Street
from 37th Aven'ue N.E. to 45th Avenue N.E. be inspected
prior to any blasting with the cost of such inspection
to be bourne by the contractor.
That a mutually acceptable testing firm, know~dgeable
in the testing of shock and vibration waves, be retained
to test all blasts which are made and submit copies
of the test r~sults to the City.
?/ -
- 2 -
That any streets in the City of Columbia Heights for
hauling of excavated materials shall be properly
maintained by the contractor including necessary surface
repairs, watering or spreading chlorides for dust control
and such other maintenance as deemed necessary due to the
usage by the contractor.
That the Performance Standards of Zoning Ordinance //462,
Section ~.]2 shall be conformed to.
BE IT FURTHER RESOLVED that the foregoing require~tents on
construction remain in effect for the duration of the
construction work on the Burlington-Northern site and that
the City Manager be authorized to issue a Special Use
Permit which shall include these foregoing requirements.
Passed this ]3th day of September~ 1971.