March 18, 2002
Mr. Mark Nagel
City of Columbia Heights
590 - 40th Avenue NE
Columbia Heights, Minnesota 55421
Re:
Letter of Interest
Architectural Evaluation of Housing Units for
Assistance in Preparation of PHA Capital Costs
Dear Mr. Nagel:
Thank you for considering TKDA for assisting you with the preparation of cost estimates associated with
two of the City's Public Housing complexes of 100 units and 45 units. We understand you have
previously prepared some cost estimates for the 100 unit complex and desire to have your costs verified.
The 45 unit complex has not been previously evaluated and these costs will need to be determined.
We are interested in providing these services to the City of Columbia Heights, and while we do not have
direct experience in preparation of your PHA performance/Evaluation Report, we have accomplished
numerous facility evaluations and cost estimates. TKDA is a full service firm including Architectural,
Landscape Architecture, Interior Design, Structural, Mechanical, and Electrical engineering in-house.
This provides the recourses necessary for most building evaluations and estimates. We are confident we
can assist you in evaluating costs associated with deferred maintenance and system life cycles for your
apartment complexes.
Our lead person will be Tim Franzen, AIA and licensed architect with 25 years experience. Mr. Franzen
has experience in preparation of reports and evaluation based on walk-through observations. Mr. Franzen
also has a Construction Administration back~ound that provides valuable experience in cost estimating.
Mr. Franzen currently is completing desig~n projects for an office building renovation and will be
available to commence walk-through of your apartment complex approximately April 8, 2002. Some
time is also budgeted for an electrical and mechanical engineer to spend one-half day on site to review
their respective systems. Mr. Franzen will be in charge of the work for TKDA, will coordinate the
mechanical/electrical resources, and prepare the cost documentation.
We anticipate the following scope of services.
1. Meeting with you to confirm the scope of the observations and categories of items/systems to
be considered. Units to be visited, representing a cross section of apartments and their
condition, will be identified. Review the documentation you have already prepared and the
categories to be estimated. ' ·
An Equal Opportunity Employer
Mr. Mark Nagel
City of Columbia Heights
March 18, 2002
Page 2
Visit the site and designated units to review the general condition of facilities to identify
deferred maintenance elements and/or failed systems that require corrections. This site visit
will include the architect (Mr. Franzen), an electrical representative, and a mechanical
representative.
Document in a brief report our findings and prepare a cost estimate of items which require
replacement or correction. This will also include a recommendation of systems that may be
nearing their life expectancy and replacement should be anticipated/budgeted within the next
five years. Example of the systems and elements to be reviewed are: water shutoff valves,
cabinets/casework, lawn irrigation system, furniture, appliances, common area/exterior paint,
window blinds, common area carpet, holding tanks, exterior windows, and water heaters.
Additional items, if observed to be deficient, will be noted.
4. Meet with you to review and present our findings, cost estimate, and recommendations.
We propose our compensation to be on an hourly rate for the individuals involved, plus reimbursable
expenses (i.e., mileage, reproduction costs, if any), with an estimated not-to-exceed amount of $6,700.
We expect the work effort could take up to three weeks to accomplish. As previously noted, we could
commence work on or shortly after April 8, 2002.
If this meets with your approval, TKDA will prepare a Letter Agreement for your review and execution.
Thank you for the opportunity to discuss this cost estimating project with you, and for considering TKDA
for these services. Please give me a call if you have any questions. (I will be back from vacation
Monday, March 25, 2002.)
Sincerely,
Dean A. Johnson, ~IA
Director of Architecture
William Deitner, PE
Vice President Building Division
DA J/mas
cc: John Powell, TKDA
Tim Franzen, TKDA
Columbia Heights Housing & Redevelopment Authori
Ch a' r .: - Date
Executive- Di Cector