HomeMy WebLinkAboutResolution No. 2004-91 RESOLUTION NO. 2004-91
BEING A RESOLUTION ACCEPTING THE FEASIBILITY REPORT AND ORDERING THE
PREPARATION OF PLANS AND SPECS FOR THE HUSET PARKWAY
WHEREAS, The Huset Parkway is a roadway along Jefferson Street fi-om 40th Avenue to 39th Avenue, continuing west
to 5th Street, and then continuing Southwest along an abandoned railroad right-of-way connecting to 37a~ Avenue.
WHEREAS, the report provides information regarding whether the proposed project is feasible, necessary and cost
effective, and
The City Council of Columbia Heights hereby receives said report on December 13, 2004.
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF COLUMBIA HEIGHTS,
MINNESOTA
The Council will consider the improvement of such streets in accordance with the report and the assessment of
abutting or benefited property for all or a portion of the cost of the improVement pursuant to Minnesota
Statutes, Chapter 429 at an estimated total cost of the improvement of $3,085,000.
A public hearing shall be held on such proposed improvements in the City Council Chmnbers at 590 40th
Avenue N.E. and the City Clerk shall give mailed and published notice of such hearing and improvement as
required by law.
3. That the location and extent of such improvements is as follows:
The Huset Parkway is a roadway along Jefferson Street from 40th Avenue to 39~ Avenue, continuing west to 5th
Street, and then continuing southwest along an abandoned railroad right-of-way connecting to 37~ Avenue.
Work includes required utility reconstruction, sub-base correction, new aggregate base, new bituminous
surfacing, new concrete curb and gutter, pond construction, bitmninous trail and sidewalk construction, tree
planting, a roundabout, restoration, miscellaneous construction items and appurtenances.
Such improvement is necessm2~, cost-effective, and feasible as detailed in the feasibility report.
Such improvement is hereby ordered as proposed in the engineering feasibility report December 6th, 2004, as
prepared by the fLrm of SEH and accepted by the council December 13th, 2004.
6. These improvements shall also be known as City Project No 2004-04.
The consulting finn of SEH and the City Engineer, Kevin Hansen, is hereby designated as the engineer(s) for
this improvement. The engineer shall prepare plans and specifications for the malting of such improvement.
Dated this 13th day of December 2004.
Offered by:
Seconded by:
Roll Call:
Kelzenberg
Ericson
Ayes: Wyckoff, Williams, Ericson, Kelzenberg Nay: Nawrocki
Attest:
(.._Patricia Muscovitz, CMC [
~eputy City Clerk/Council $ecretary