HomeMy WebLinkAboutResolution No. 2004-13RESOLUTION 2004-13
BEING A RESOLUTION ORDERING IMPROVEMENT AND
THE PREPARATION OF PLANS FOR ZONE 7A STREET REHABILITIATION
CITY PROJECT 0402
WHEREAS, Resolution 2004-07 of the Columbia Heights City Council adopted the 9th day of February,
2004, frxed a date for a Council heating on the proposed improvement bounded on Central Avenue on the
east, 37th Avenue on the south, University Avenue Service Road on the west, and 40'h Avenue on the north,
and 7th Street from 40t~ Avenue to 42nd Avenue,
AND WHEREAS, ten days' mailed notice and two published notice of the heating a week apart was given,
and the heating was held thereon the 9th day of March, 2004, at which all persons desiring to be heard were
given an opportunity to be heard thereon.
WHEREAS, the Council determines to proceed with this local improvement, a portion of the cost being
defrayed by special assessments under Charter provisions.
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL 'OF THE CITY OF COLUMBIA
HEIGHTS, M/NNESOTA:
1. That the location and extent of such improvements i.s as follows:
Full street reconstruction of 7th Street, 40th to 42nd Avenues, Quincy Street, 37th to 39m
Avenues, Quincy Street south of 40m Avenue, Jackson Street, 37th to 40th Avenues and Van
Buren Street, 37m to 40th Avenues.
Work includes required utility reconstruction, new gramflar sub-base if needed, new aggregate
base, new concrete curb and gutter with driveway aprons, required water service replacement
and sanitary sewer service repair, required concrete or bituminous driveway and walk/step
replacement, sod restoration, miscellaneous construction items, and appurtenances.
2. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility
report.
3. Such improvement is hereby ordered as proposed in the Council Resolution adopted 9th day
of Febmary, 2004.
4. These improvements shall also be known as P:I.R. #1083 - Project 0402.
5. The City Engineer, Kevin Hansen, is hereby designated as the engineer for this improvement.
The engineer shall prepare plans and specifications for the making of such improvement.
Adopted by the Council this 9th day of March, 2004.
Offered by: Kelzenberg
Seconded by: Williams
Roll Call: Aye: Wyckoff, Williams, Ericson, Kelzenberg
Absent: Nawrocki
Attest:
~atricia Muscovitz, CMC
Deputy City Clerk/Council Secretary
·
~~"6~' Julieune Wyck° ff'~ ~J ~)